No.Condition Text
1.Application for approval of reserved matters must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun not later than whichever is the later of the following dates:- a) the expiration of five years from the date of this permission; or b) the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved. The reason for this condition:- Required to be imposed pursuant to Section 92 of the Town and Country Planning Act 1990.
2.No development whatsoever shall take place until full details of the siting, design, external appearance of the development and means of access have been submitted to and approved by the Local Planning Authority and the development shall be carried out strictly in accordance with such approved details. Reason for the condition is:- Such details have not been submitted as part of this application.
3.The dwelling shall be of single storey construction and notwithstanding the provisions of the Town and Country Planning General Development Orders, 1988-90, no dormer window or other openings to the roofspace shall be provided unless otherwise specified in writing by the Local Planning Authority. The reason for the condition is:- the interests of the residential amenities of the occupiers of the nearby properties.
4.The to be submitted under condition 2 above shall include the provision of an access with gate posts set back 4.5 metres and 45 degree splays (with gates to open inwards) together with the provision of a turning area to be constructed within the site curtilage. The reason for the condition is:- In order to provide adequate access to and from the site.
5.The access shall be constructed in accordance with Norfolk County Council residential access apecification prior to the occupation of the dwelling hereby permitted. The reason for the condition is:- To ensure the provision of an adequate access to serve the development proposed.