| No. | Condition Text |
|---|---|
| 1. | The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2. | NOTES - Please read the following notes carefully:- |
| 3. | The applicant is reminded of the need to obtain a works licence from the Broads Authority prior to commencing the works hereby approved (tel: 01603 610734). In addition, the works need the prior written consent of the Environment Agency under the Water Resources Act 1991 in respect of works in, under, over or within 9 metres of the top of the bank of the main river or fluvial flood defence (tel: Andrew Meddle on 01473 706016). |