| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the
date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country
Planning Act 1990. |
| 2. | The colour of the proposed roof cladding shall be either "Forest Green" or
"Marine Blue" as indicated on the sample colour swatch submitted with the
application.
The reason for the condition is :-
For the avoidance of doubt and in the interests of the visual amenities of
the locality. |
| 3. | No development shall take place until full details of soft landscape works
adjacent to the western boundary of the site have been submitted to and
approved in writing by the Local Planning Authority and these works shall
be carried out as approved. The soft landscape works shall include
planting plans; written specifications (including cultivation and other
operations associated with plant and grass establishment); schedules of
plants noting species, plant sizes and proposed numbers/densities where
appropriate; and an implementation programme.
The reason for the condition is :-
In the interests of the visual amenities of the locality.
continued on next page :- |
| 4. | All soft landscape works shall be carried out in accordance with the
approved details. The works shall be carried out before the salt store is
brought into use or in accordance with the programme agreed with the Local
Planning Authority.
The reason for the condition is :-
In the interests of the visual amenities of the locality. |
| 5. | NOTES - Please read the following notes carefully:- |
| 6. | 1. Attention is drawn to the attached letter received from the King's Lynn
Consortium of Internal Drainage Boards.
2. A copy of the application has been sent to the Environment Agency -
Anglian Region for comment. Any response from the Agency will be forwarded
direct under separate cover. |