| No. | Condition Text |
|---|
| 1. | No development whatsoever shall take place until full details of the
design, external appearance, and landscaping of the development have
have been submitted to and approved by the Local Planning
Authority and the development shall be carried out strictly in accordance
with such approved details.
The reason for the condition is:-
Such details have not been submitted as part of this application. |
| 2. | Application for approval of reserved matters must be made not later than
the expiration of three years beginning with the date of this permission
and the development must be begun not later than whichever is the later of
the following dates:-
a) the expiration of five years from the date of this permission;
or
b) the expiration of two years from the final approval of the reserved
matters or, in the case of approval on different dates, the final approval
of the last such matter to be approved.
The reason for this condition:-
Required to be imposed pursuant to Section 92 of the Town and Country
Planning Act 1990. |
| 3. | The development shall be carried out in accordance with the revised plan
received by the Local Planning Authority on 19th February 1999.
The reason for the condition is :-
For the avoidance of doubt. |
| 4. | Prior to or when an application for full planning permission is submitted,
a scheme to assess and deal with the likely contamination of the site shall
be submitted to and approved in writing by the Local Planning Authority
in consultation with the Environmental Health Department.
The reason for the condition is:-
Contamination of the site is likely to have occurred due to storage
spillage, leakage or disposal of raw material and pipework, and so as to
ensure any contamination is correctly dealt with and that no risk
from possible explosive residue is likely to arise from the site. |
| 5. | The details to be submitted as required by condition 4 shall include a
comprehensive soil survey to acertain whether the land is contaminated. The
scheme shall identify the location and nature of any underground structures
on the site and assess suitable remedial action for the structures and such
a scheme shall be agreed in writing with the Local Planning Authority in
consultation with the Environmental Health Department.
The reason for the condition is:-
To ensure that any contamination of the site is effectively dealt with
prior to the site being developed for residential purposes. |
| 6. | No residential unit shall be occupied until the scheme for decontamin-
ation of the site has been fully implemented to the satisfaction of the
Local Planning Authority in consultation with the Environmental Health
Department.
The reason for the condition is:-
In the interests of the residential amenities of the occupiers of the
properties. |
| 7. | The details to be submitted in condition 1 above shall incude the provision
of a 2 metre x site extremity visibility splay at the entrance to the site
with the width of the access being reduced to 4.5 metres.
The reason for the condition is:-
To ensure the provision of a satisfactory highway approach. |
| 8. | The details submitted to accord with condition 1 shall include adequate
provision for the maintenance of the dyke at the rear of the site.
The reason for the condition is:-
To ensure the drainage syatem can be adequately maintained. |
| 9. | NOTES - Please read the following notes carefully:-
If hazards are identified on the site from any form of contamination as
a result of the survey required by condition 5, the results of the survey
shall be utilised to undertake a site specific risk assessment to consider
the risks to:-
a) Water resources, including drinking water
b) surrounding land
c) building materials
d) cultivated trees and plants
e) wild life
f) future users of the site and
g) any other persons. |