1.The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2.The use of the premises for trailer repairs shall be ancillary to the adjoining warehouse use and shall not be used for any other purpose without the prior written consent of the Local Plannig Authority The resason for the condition is:- To ensure the use of the premises takes place in the manner contemplated by the Planning Authority.
3.Notwithstanding the details shown on the submitted drawing details shall be submitted for the approval of the Local Planning Authority showing foul water from the site being discharged into the foul sewage system and no part of the development hereby permitted shall be commenced until such details have been approved and the development shall not be brought into use until the drainage system as approved has been completed. The reason for the condition is:- To ensure the provision of a satisfactory drainage system to prevent pollution of the freshwater dyke system.
4.Prior to any work commencing on the development hereby permitted details of any lighting to be installed on the site shall be be submitted for the approval of the Local Planning Authority and such works completed prior to the trailer park being being brought into use. The reason for the condition is:- In the interest of the residential amenities of the occuiers of the nearby properties.
5.No working refridgerated units shall be parked on the site and the pressure washer used outside the following hours:- 08.00 - 18.00 hrs Monday to Friday 08.00 - 13.00 hrs Saturdays and at no time on a Sunday or Bank Holiday The reason for the condition is:- For the avoidance of doubt and in the interests of the residential amenities of the occupiers of the nearby properties.
6.The development shall be carried out in accordance with the revised layout plan received by the Local Planning Authority on 5th March 1999. The reason for the condition is :- For the avoidance of doubt.
7.Before the development is commenced a scheme of planting and landscaping shall be submitted for the approval of the Local Planning Authority and the planting of trees and shrubs shall be carried out in accordance with the scheme as approved within one year of the approval. Any trees and shrubs so planted which dies within 5 years shall be replaced within one year by the applicants or their sucessors in title. The reason for the condition is:- To enhance the visual amenities of the locality
8.The buffer strip indicated on the approved plan shall be planted in accord- ance with a scheme as approved to be submitted to and approved by the Local Planning Authority and the scheme as approved shall be completed before the development hereby approved is first brought into use. Any trees and shrubs which die decome seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority agree in writing to any variation. The reason for the condition is:- To ensure the provision of the buffer strip in the interests of the visual amenities of the locality and the residential amenities of the occupiers of the nearby dwellings.
9.NOTES - Please read the following notes carefully:- The Environmental Health Officer advises the site is adjacent to a small area of landfill which is producing localised pockets of landfill gas. Moreover the application site is also a former marsh area where naturally produced methane from the peaty soil is present. The applicant should be advised of the need to incorporate gas protection measures within the design of the buildings and is strongly recommended to install gas alarms in the buildings.
10.The applicant's attention is drawn to the attached letter from the Environment Agency (Anglian Region) and the need to comply fully with their requirements.