1.The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2.The development shall be carried out in accordance with the revised plan received by the Local Planning Authority on 15th December 1998 in respect of the revised layout of the junction of the existing private road and the new access to the Waveney Valley Holiday Village. The reason for the condition is:- To ensure the permission relates to the correct documents.
3.Foul drainge from the developmnt hereby permitted, and water and backwash from the swimming pool, shall be discharged only to the main foul sewer; only clean surface water shall be discharged to any soakaway. The reason for the condition is:- To avoid overloading the sewerage system.
4.All planting and, seeding or turfing comprised in the approved details of landscaping for each phase of the development as shown on drawing 5196-2 shall be carried out in the first planting and seeding seasons following the commencement of that phase, any trees or plants which within a period of five years from the completion of the development die, are removed or become seriously damaged or dieseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written consent to any variation. The reason for the condition is:- In the interests of the visual amenities of the locality.
5.Unless otherwise agreed in writing by the Local Planning Authority, the facilities block indicated on drawing 5196-1A, shall only be open to those resident on the site or in the Waveney Valley Holiday Village. The reason for the condition is:- To ensure the development is used in the manner contemplated by the Local Local Planning Authority on the grant of this permission.
6.No caravan shall be stationed on the site shall be occupied other than as holiday accommodation. The reason for the condition is:- The accommodation is unsuitable for all year round occupation.
7.The development hereby permitted shall not be carried out otherwise than in accordance with a phased programme of works, the details of which shall have been submitted to and approved by the Local Planning Authority prior to the commencement of development of the site, and the construction of each phase of serviced caravan bases shall not begin until works comprised in the preceding phase of the development are complete, unless the Local Planning Authority gives written consent to any variation. The reason for the condition is:- To ensure the development proceeds in an orderly manner.
8.No pedestrian or vehicular access shall be formed between the new access road and Porters Loke without the prior permission, in writing of the Local Planning Authority. The reason for the condition is:- Porters Loke is not suitable to cater for additional traffic.