| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the
date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country
Planning Act 1990. |
| 2. | Before the use hereby approved is first brought into operation car
parking, servicing and storage facilities shall be provided within the
site in accordance with details to be submitted to and approved by the
Local Planning Authority.
The reason for the condition is :-
To provide for the parking of vehicles off the highway in the interests
of highway safety as no details of such provision were submitted with
the application. |
| 3. | All oil, fuel or chemicals storage tanks,ancillary handling facilities
and equipment including pumps/valves shall be contained within an
impervious bunded area of at leat 110% of the tank capacity.The
drainage sysstem of the bund shall be sealed with no discharge to any
watercourse,land or underground strata.Associated pipework should be
located above ground and protected from accidental damage.All filling
points and tank overflow pipe outlets should be detailed to discharge
downwards into the bund.
The reason for the condition is :-
To prevent pollution of the water environment. |
| 4. | All foul sewage or trade effluent including cooling water containing
chemical additives,or vehicle washing water,including steam cleaning
effluent shall be discharged to the foul sewer.
The reason for the condition is :-
To prevent pollution of the water environment. |