| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the
date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country
Planning Act 1990. |
| 2. | The development hereby permitted shall be carried out in accordance with
the amended plan, Drawing No. VA231/1 Issue B, received by the Local
Planning Authrority on 30th July 1997.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | No development shall take place until there has been submitted to and
approved by the Local Planning Authority a scheme of landscaping, which
shall include indications of all existing trees and hedgerows on the land,
and details of any to be retained, together with measures for their
protection in the course of development.
The reason for the condition is :-
In the interests of the visual amenities of the locality.
continued on next page :- |
| 4. | All planting, seeding or turfing comprised in the approved details of
landscaping shall be carried out in the first planting and seeding season
following the building being brought into use or the completion of the
development, whichever is the sooner; and any trees or plants which within
a period of 5 years from the completion of the development die, are removed
or become seriously damaged or diseased shall be replaced in the next
planting season with others of similar size and species, unless the Local
Planning Authority gives written consent to any variation.
The reason for the condition is :-
In the interests of the visual amenities of the locality. |
| 5. | No development shall take place until full details of the operation of the
proposed generator, including measures for the attenuation of noise and
smell emissions, have been submitted to and approved by the Local Planning
Authority.
The reason for the condition is :-
To ensure that the operation of the building does not adversely affect the
residential amenity of nearby properties. |
| 6. | Planned, programmed maintenance including the testing of the generator
shall only be carried out between 9.00 a.m. and 5.00 p.m. Monday to Friday.
There shall be no testing on Saturdays, Sundays or bank holidays.
The reason for the condition is :-
To ensure that the operation of the building does not adversely affect the
residential amenity of nearby properties. |
| 7. | Any standby fuel tank shall be contained within a bund having the capacity
to hold the the full contents of the tank plus 10%. All connections for
filling etc. shall be within the confines of the bund. There shall be no
drainage of the bund.
The reason for the condition is :-
To prevent pollution of the water environment. |
| 8. | The equipment building shall not be brought into use until the "site
access and turning area" indicated on the amended plan mentioned in
condition No. 2 has been drained and surfaced, and that area shall not
therafter be used for any purpose other than the parking and manoeuvring
of vehicles.
The reason for the condition is :-
To provide for the parking of vehicles off the highway and to enable
vehicles to enter and leave the site in a forward gear in the interests
of highway safety. |
| 9. | Notwithstanding the provisions of the Town and Country Planning (General
Permitted Development) Order 1995 (or any order revoking and re-enacting
that Order with or without modification), any fencing to be erected on the
site shall be in accordance with details to be submitted to and approved,
in writing, by the Local Planning Authority.
The reason for the condition is :-
In the interests of the visual amenities of the locality.
continued on next page :- |
| 10. | Within 3 months of the equipment building being brought into use any
damage caused, during the course of the proposed construction works, to
the surface of Low Road (which is designated as a "Carriage Road used
mainly as a Public Footpath" under relevant legislation) shall be repaired
in accordance with details to be submitted to and approved by the Local
Planning Authority.
The reason for the condition is :-
In order to maintain public access along this right of way. |
| 11. | NOTE - Please read the following note carefully:- |
| 12. | During the course of the proposed construction works the applicant should
make propoer provision to maintain safe public access along the route of
the right of way. |