1.No development whatsoever shall take place until full details of the siting, design, external appearance, means of access and landscaping of the development have been submitted to and approved by the Local Planning Authority and the development shall be carried out strictly in accordance with such approved details. The reason for the condition is:- Such details have not been submitted as part of this application.
2.Application for approval of reserved matters must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun not later than whichever is the later of the following dates:- a) the expiration of five years from the date of this permission; or b) the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved. The reason for this condition:- Required to be imposed pursuant to Section 92 of the Town and Country Planning Act 1990.
3.The details to be submitted in accordance with condition 2 above shall include provision for Open/Recreation Space and Children's Playspace in accordance with the Borough Council's adopted standards. The reason for the condition is :- To ensure that adequate provision is made for Open/Recreation Space and Childrens' Playspace to serve the proposed development.
4.No works shall commence on the site until such time as detailed plans of the roads, footways, foul and "on-site" surface water drainage have been submitted and approved by the Local Planning Authority, these details shall include the provision of measures to attenuate flows flows from the site. The reason for the condition is:- To ensure the construction of estate roads are of a standard suitable for To ensure the construction of estate roads are of a standard suitable for adoption as County roads and to ensure provision of a satisfactory means of surface water drainage and to prevent overloading of the existing drainage system.
5.No works shall be carried out on roads, footways, foul and surface water sewers otherwise than in accordance with the specifications of the Local Planning Authority. The reason for the condition is:- To ensure the construction of estate roads are of a standard suitable for adoption as County roads.
6.No dwelling shall be occupied until such time as a road and footway have been constructed from the dwelling to the adjoining County road to a standard to be agreed, in writing, with the Local Planning Authority. The reason for the condition is:- To provide the residents of the estate with satisfactory highway approaches to their property.
7.Before any building takes place an "off-site" surface water drainage system shall be constructed from the site, in accordance with details to be agreed in writing, by the Local Planning Authority in consultation with Anglian water Services, these details shall include the provision of measures to attenuate flows from the site. The reason for the condition is:- To ensure the provision of a satisfactory means of surface water drainage and to prevent overloading of the existing drainage system.
8.No development approved by this permission shall be commenced until a scheme for the provision of surface water drainage has been approved by the Local Planning Authority. Such scheme shall be completed in accordance with the approved plans before commencement of development. The reason for the condition is:- To prevent the increased risk of flooding by ensuring the provision of a satisfactory means of surface water disposal.
9.Prior to being discharged into any watercourse, surface water sewer or soakaway system, all surface water from impermiable parking areas and hard standings shall be passed through trapped gullies with an overall capacity compatible with the site being drained. The reason for the condition is:- To prevent pollution of the water environment.
10.All trees other than shown as to be removed on the approved plans shall be adequately protected during the period of construction by the erection of a braced scaffold vertical framework at least 1.2 metres high (to BS 5837) enclosed by either cleft chestnut pale fencing to (BS 1722 : Part4) or chain link fencing (to BS 1722 : Part 1), which shall extend beyond either the outermost branch-spread of the tree (the dripline) or the root system, whichever is the greater distance. The reason for the condition is:- The existing trees represent an important visual amenity which the Local Planning Authority consider should be substantially maintained.
11.No work on site (including the pre-construction delivery of equipment or materials or the creation of site accesses) shall be commenced until all details of the protective barrier have been agreed to, in writing, by the Borough Planning and Development Officer and the protection barrier erected to his satisfaction. The reason for the condition is:- To ensure the development proceeds in an orderly manner.
12.There shall be no raising or lowering of levels; no storage of soil, debris or building materials; and no passage of vehicles or plant within the protective barrier under any circumstances except with the written consent and advice of the Borough Planning and Development Officer on additional protective measures. The reason for the condition is:- For the avoidance of doubt and to ensure the existing trees are protected during the course of the development.
13.Any tree that suffers injury during the period of construction or dies within 3 years of the development shall be replaced with a tree of a suitable size and species to the satisfaction of the Borough Planning and Development Officer in the first available planting season thereafter, all works to be carried out to BS 4428 : 1989 "Code of Practice for General Landscape Operations". The reason for the condition is:- To ensure the provision of replacement trees to maintain the existing planting on the site, in the interests of the visual amenities of the locality.