| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the
date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country
Planning Act 1990. |
| 2. | No dwelling shall be occupied until the 2 metre wide footpath has been
constructed along the west side of of the highway turning head in
accordance with the Norfolk County Council's Highways specification.
The reason for the condition is :-
In the interests of pedestrian safety. |
| 3. | No development shall be commenced until a detailed landscaping scheme
showing the treatment of all areas of hard and soft landscaping including
any means of enclosure to be erected has been submitted to and approved
by the Local Planning Authority.All planting in accordance with the
scheme as may be approved shall be completed within 1 year from the date
on which any dwelling is first occupied and any trees or shrubs so
planted which die within 3 years shall be replaced by the applicants or
their successors in title.
The reason for the condition is:-
To enhance the visual amenities of the locality. |
| 4. | The details to be submitted as required by condition 3 shall include
details of the proposed means of enclosure for all the external
boundaries of the application site and no dwelling shall be first
occupied until the approved means of enclosure has been provided.
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of the
adjacent property as no such details have been submitted as part of the
application. |
| 5. | None of the dwellings shall be first occupied until the parking area and
access thereto have been constructed in accordance with the details to
be approved under condition 3.
The reason for the condition is :-
In order to ensure satisfactory off-street parking to meet the needs
generated by the development in the interests of highway safety. |
| 6. | Notwithstanding the provisions of the Town and Country Planning (General
Permitted Development) Order 1995 no gates shall be hung on any part of
the vehicular access to any of the dwellings.
The reason for the condition is :-
In order to ensure the provision of of proper access and turning
facilities in the interests of highway safety. |
| 7. | Notwithstanding the provisions of the Town and Country Planning (General
Permitted Development) Order 1995 no extensions or garages shall be
erected on any of the plots without the prior permission of the Local
Planning Authority.
The reason for the condition is :-
To enable the the Local Planning Authority to retain control over any
future development of the plots which are restricted in size. |
| 8. | All the dwellings hereby approved shall be constructed with ramped
approaches, level standings at doorways, flush thresholds and wide
(838mm.minimum) easy to open to open doors.
The reason for the condition is :-
To ensure that the dwellings are readily visitable by disabled persons
in accordance with the Council's policy contained in the Great Yarmouth
Borough-Wide Local Plan.
Continued on next page. |
| 9. | Before any development is commenced a detailed drawing providing for an
increased depth of the bedroom windows of the disabled person's bungalow
shall be submitted to and approved by the Local Planning Authority.
The reason for the condition is :-
To ensure that the accommodation is suitable for a wheelchair user to be
able to look out of the window when seated.
Informative Note.
The applicant is advised that under the terms of the Water Resources Act
1991 and the Land Drainage Byelaws the prior written consent of the
Environment Agency is required for any proposed works or structures in,
under, over or within 9 metres of the top of the bank of the main
river (River Bure). |
| 10. | No works shall commence on site until such time as details of the slab
levels of the dwellings in relation to existing ground levels have been
submitted to and approved by the Local Planning Authority.
The reason for the condtions is:-
To ensure that the development takes place in the manner contemplated by
the Local Planning Authority and to retain control over any significant
changes in levels within the site. |