Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2.All oil, fuel or chemical tanks, ancillary handling facilities and equipment including pumps/valves shall be contained within an impervious bunded area of at least 110% of the tank capacity or largest tank if multiple storage.The drainage system of the bund shall be sealed with no discharge to any watercourse,land or underground strata.Associated pipework should be located above ground and protected from accidental damage.All filling points and tank overflow pipe outlets should be detailed to discharge downwards into the bund. The reason for the condition is :- To prevent pollution of the water environment.
3.Prior to being discharged into any watercourse, surface water sewer or soakaway system, all surface water drainage from impermeable parking areas and hard standings shall be passed through an oil separator designed and constructed to have a capacity and details compatible with the site being drained.Roof water shall not pass through the separator. The reason for the condition is :- To prevent pollution of the water environment.
4.All foul sewage or trade effluent, including cooling water containing chemical additives, or vehicle washing water, including steam cleaning effluent shall be discharged to the foul sewer. The reason for the condition is :- To prevent pollution of the water environment.
5.Informative Note. The applicant's attention is drawn to the attached letter from the Environment Agency and the need to comply fully with their requirements. This permission does not purport to convey leasehold consent for which a separate application must be made to the Borough Valuer and Estates Surveyor, Town Hall, Great Yarmouth.