| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the
date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country
Planning Act 1990. |
| 2. | No work shall commence until the exact type and colour of the roofing
materials have been submitted for the approval of the Local Planning
Authority.
The reason for the condition is:-
In the interests of the visual amenities of the area as precise details of
the materials have not been submitted. |
| 3. | The premises shall not be occupied until the conversion work has been
carried out entirely in accordance with the approved plans
The reason for the condition is:-
In order to ensure a satisfactory standard of accommodation. |
| 4. | Notwithstanding the provisions of the Town and Country Planning (General
Permitted Development) Order 1995 ( or any order revoking and re-enacting
that Order) the dwellings shall not be extended nor any windows, vents or
flues inserted in the eastern elevation of the building without the prior
consent in writing of the Local Planning Authority.
The reason for the condition is:-
To enable the Local Planning Authority to retain control over any
extensions to the dwellings in the interests of residential amenity. |
| 5. | NOTES - Please read the following notes carefully:-
Anglian Water advise that the applicant should note that a Section 24 sewer
passes through the site and no buildings should normally be erected over or
within 3 metres of this pipework, however in certain cases may be prepared
to relax this ruling. if any diversion works are proposed, the cost must
be met by the developer.
ATTENTION IS DRAWN TO THE FACT THAT THE DEVELOPMENT HEREBY APPROVED IS
SUBJECT TO THE TERMS OF AN AGREEMENT DATED 00TH OCTEMBER 0000 PREPARED
UNDER THE PROVISIONS OF SECTION 106 OF THE TOWN AND COUNTRY PLANNING ACT
1990. |