| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the
date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country
Planning Act 1990. |
| 2. | The development shall be constructed in accordance with detailed
specifications which shall have first been submitted to, and approved in
writing by, the Local Planning Authority.
The reason for the condition is:-
To ensure the new mooring cut is properly constructed. |
| 3. | The boat cut hereby permitted shall be used solely in conjunction with the
occupation of 62 Repps Bank and shall not be used as a separate mooring and
following the construction of the boat cut there shall no longer be mooring
on the main river.
The reason for the condition is:-
To ensure that the development complies with the planning policies for the
area. |
| 4. | NOTES - Please read the following notes carefully:- |
| 5. | Under the terms ofthe Water Resources Act 1991 and the Land Drainage
Byelaws, the prior written consent of the Environment Agency is required
for any proposed works or structures in, under, over or within 9 metres of
the top of the bank of the main river (River Thurne).
The applicant is advised of the requirement of a Works Licence from the
Broads Authority prior to commencing work.
Repps Martham and Thurne Internal Drainage Board ask that adequate steps be
taken to prevent seepage from the main river into their low level system. |