Great Yarmouth Borough Council Portal
No.Condition Text
1.Application for approval of reserved matters must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun not later than whichever is the later of the following dates:- a) the expiration of five years from the date of this permission; or b) the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved. The reason for this condition:- Required to be imposed pursuant to Section 92 of the Town and Country Planning Act 1990.
2.No development whatsoever shall take place until full details of the siting, design, external appearance, means of access and landscaping of the development have been submitted to and approved by the Local Planning Authority and the development shall be carried out strictly in accordance with such approved details. The reason for the condition is:- Such details have not been submitted as part of this application.
3.Except where removal is necessary to allow construction of the new vehicular access, the existing hedge along the front of the application site shall be retained. Reason: In the interests of the visual amenities of the locality.
4.No dwelling shall be occupied until the garage or parking space relating to that dwelling has been completed. The reason for the condition is:- To ensure that the development is satisfactorily completed.
5.The access provided to the site during building operations shall be laid out, formed and constructed to the satisfaction of the Local Planning Authority before any operations commence and be maintained to the satisfaction of these Authorities until such time as the permanent access is constructed in accordance with the conditions attached to this consent. The reason for the condition is:- In the interests of highway safety.
6.Prior to the occupation of either of the dwellings hereby approved the access drive and junction onto the main road shall have been constructed in accordance with detailed specifications that shall have first been submitted to,and approved in writing by, the Local Planning Authority. The reason for the condition is:- To ensure that the development is served by an acceptable access.