Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2.Any facilities for the storage of oils, fuels or chemicals shall be sited on impervious bases and surrounded by impervious bund walls. The volume of the bunded compound should be at least equivalent to the capacity of the tank plus 10%. If there is multiple tankage, the compound should be at least equivalent to the capacity of the largest tank, plus 10%. All filling points, vents, gauges and sight glasses must be located within the bund. The drainage system of the bund shall be sealed with no discharge to any watercourse, land or underground strata. Associated pipework should be locted above ground and protected from accidental damage. All filling points and tank overflow pipe outlets should be detailed to discharge into the bund. The reason for the condition is:- To prevent pollution of the water environment.
3.There shall be no discharge of foul or contaminated drainage from the site into either groundwater or any surface waters, whether direct or via soakaways. The reason for the condition is:- To prevent pollution of the water environment.
4.Prior to any work commencing on the development hereby permitted details of any flues on extractor fans shall be submitted for the approval of the Local Planning Authority and such works as agreed shall be carried out entirely in accordance with the approved details. The reason for the condition is:- For the avoidance of doubt and to ensure the amenities of the occupiers of the adjoining premises are not adversely affected.
5.NOTES - Please read the following notes carefully:- The applicant's attention is drawn to the attached comments of the Council's Environmental Health Officer and the need to comply fully with these requirements. The applicant is reminded that any works in close proximity to the overhead electric transmission line should meet the requirements of Eastern Electricity.
6.The applicant's attention is drawn to the comments of the County Waste Disposal Officer regarding measures that are neccessary to safeguard against any potential hazard arising from landfill gas in this area (letter attached). The applicant is also advised to contact the Chief Building Control Officer and the Environmental Health Officer to ascertain any other special measures that may be necessary.