No.Condition Text
1.The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2.Within two months of the date of this permission,or such longer period as may be agreed in writing with the Local Planning Authority,a detailed planting scheme providing for a substantial reinforcement of the existing shrub planting along the northern boundary of the site with standard/half- standard size trees shall be submitted to and approved by the Local Planning Authority and all planting in accordance with the scheme as may be approved shall be completed before 28th.February 1996. The reason for the condition is :- To ensure that an adequate screen is provided between the site and the adjoining open countryside in the interests of the visual amenities of the area.
3.Within two months of the date of this permission 36 of the car parking spaces shown on the plan received with the applicants letter on 15th. December 1994 shall be levelled,hardened and surfaced to the approval of the Local Planning Authority and the remainder of the 45 car parking spaces shown on the same plan shall be levelled,hardened and surfaced to the approval of the Local Planning Authority before the workshop hereby approved is first brought into use. The reason for the condition is :- For the avoidance of doubt and to ensure that adequate off-street parking space is provided to serve the existing and proposed buildings.
4.If at any time it is deemed that the parking provision shown on the plan received by the local Planning Authority on 15th.December 1994 is inadequate to cater for the traffic movements generated by the use of the site 18 additional parking spaces shall be formed to accord with the Council's adopted standards. The reason for the condition is :- In order to ensure satisfactory off-street parking to meet the needs generated by the development in the interests of highway safety.
5.Within six months of the date of this permission,or such longer period as may be agreed in writing,the site access road shall be constructed between the parking area adjacent to the existing office accommodation and the estate road in accordance with details to be submitted to and approved by the Local Planning Authority. The reason for the condition is :- To ensure the provision of satisfactory highway approaches to and within the site in the interests of highway safety.
6.Before the workshop hereby approved is first brought into use the site access road between the east end of the building and the estate road shall be constructed in accordance with details to be submitted to and approved by the Local Planning Authority. The reason for the condition is :- To ensure the provision of satisfactory highway approaches to the development in the interests of highway safety.
7.Within three months of the date of this permission,or such longer period as may be agreed in writing,details of the surfacing work to be carried out together with the phasing of such work shall be submitted to and approved by the Local Planning Authority and the work shall not be carried out other than in accordance with the details as may be approved. The reason for the condition is :- For the avoidance of doubt as no such details were submitted as part of the application.
8.No development approved by this permission shall be commenced until a scheme for the disposal of foul and surface water has been implemented in accordance with details to be submitted to and approved by the Local Planning Authority in consultation with the N.R.A. The reason for the condition is :- To prevent pollution of the water environment.
9.Prior to being discharged into any watercourse, surface water sewer or soakaway system, all surface water drainage from parking areas and hardstandings shall be passed through an oil interceptor designed and constructed to have a capacity compatible with the site being drained.Roof water shall not pass through the interceptor. The reason for the condition is :- To prevent pollution of the water environment.
10.Adequate measures shall be taken to ensure that no nuisance is caused to occupiers of neighbouring sites from grit, dust, fumes, odour, droplets or any other means. The reason for the condition is :- To prevent injury to the amenities of the area.
11.This permission insofar as it relates to the portacabin offices and containers is for a temporary expiring on 1st.January 1997 and unless on or before that date application is made for an extension of the period of permission and such application is approved by the Local Planning Authority the structures shall be removed. The reason for the condition is :- In order to retain control over the buildings which are of a temporary nature and in the interests of the visual amenities of the area.
12.The temporary office accommodation hereby approved shall only be used by Rigblast Services Limited in connection with the operations carried on within the site and shall not be let as separate office accommodation. The reason for the condition. to ensure that the use of the site takes place in the manner contemplated by the Local Planning Authority on the grant of this permission. Informative Notes. a) The applicant's attention is drawn to the attached letter from the National Rivers Authority and the need to fully comply with their requirements. b) The applicant is reminded that the temporary consent in respect of the former Super Serv portacabin offices has expired and that their use must be discontinued.