| No. | Condition Text |
|---|---|
| 1. | The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2. | Before the facilities hereby approved are first brought into operation the site shall be enclosed with a suitable wall, except for the access gates and fencing to the E.E.B.transformers,and the means of enclosure shall not be constructed other than in complete accordance with details to be submitted to and approved by the Local Planning Authority. The reason for the condition is :- For the avoidance of doubt and in the interests visual amenity. |
| 3. | No development shall take place within the application site until the applicant has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation which has been submitted by the applicant and approved by the Planning Authority. The reason for the condition is :- In order to enable investigation and recording of this site of archaeological interest to take place during the period of building and engineering works. Informative Notes. a) The applicant's attention is drawn to the attached letter from the N.R.A.and the need to comply fully with their requirements. b) The applicant is advised that consultations should take place with the Borough Environmental Health Officer to ensure that adequate measures are taken to prevent dust,smell or noise nuisance to the occupiers of adjacent property at the construction stage. |