| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the
date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country
Planning Act 1990. |
| 2. | Prior to the occupation of the dwelling hereby permitted the access gate or
gates hung to open inwards, shall be set back a minimum distance of 4.5
metres from the edge of the adjoining highway carriageway and a hedge,
fence or wall not exceeding 1 metre in height above highway carriageway
level shall be splayed at an angle of 45 degrees from each of the (outside)
gateposts.
The reason for the condtion is:-
To provide for vehicles to stand clear of the highway carrageway in the
interests of highway safety whilst the gates are being opened or closed. |
| 3. | The dwelling shall not be occupied until the access and turning area
shown on the submitted plan has been laid out, surfaced and drained in
accordance with the approved plan and that area shall not be used
thereafter for any purpose other than the parking and turning of vehicles.
The reason for the condition is:-
In order to ensure the provision of proper access and turning facilities
in the interests of highway safety. |
| 4. | Prior to the occupation of the dwelling hereby approved the existing
garage access shall be stopped up and the garage modified or replaced to
be accessed from the new access onto the main road.
The reason for this condition is:-
In the interests of highway safety. |
| 5. | No development shall take place until there has been submitted to and
approved by the Local Planning Authority a scheme of landscaping, which
shall include indications of all existing trees and hedgerows on the land,
and details of any to be retained, together with measures for their
protection in the course of development.
The reason for the condition is:-
In the interests of the visual amenities of the locality. |
| 6. | All planting, seeding or turfing comprised in the approved details of
landscaping shall be carried out in the first planting and seeding season
following the occupation of the buildings or the completion of the
development, whichever, is the sooner, and any trees or plants which within
a period of 5 years from the completion of the development die, are removed
or become seriously damaged or diseased shall be replaced in the next
planting season with others of similar size and species, unless the Local
Planning Authority gives written consent to any variation.
The reason for the condition is:-
In the interests of the visual amenities of the locality. |
| 7. | The foul drainage from the proposed development shall be discharged to a
septic tank and soakaway system which meets the requirements of British
Standard BS 6297: 1983 and which complies with the following:-
(a) there is no connection to any watercourse or land drainage system and
no part of the soakaway system is situated within 10 metres of any ditch
or watercourse.
(b) porosity tests are carried out to the satisfaction of the Local
Planning Authority to demonstrate that suitable subsoil and adequate land
area is available for the soakaway (BS 6297:1983 refers).
The reason for the condition is:-
To prevent pollution of the water environment. |
| 8. | No development approved by this permission shall be commenced until a
scheme for the provision and implementation of foul drainage works has
been approved by, and implemented to the reasonable satisfaction of, the
Local Planning Authority.
The reason for the condition is:-
To prevent pollution of the water environment. |
| 9. | NOTES - Please read the following notes carefully:- |
| 10. | The applicant's attention is drawn to the attached letter from the National
Rivers Authority (Anglian Region) and the need to comply fully with their
requirements. |