| 1. | Condition 11 of pp. 06/23/0056/F covers the submission of existing site levels and proposed ground levels and finished floor levels. This is required to include (i) a full site survey showing all existing site levels above ordnance datum including the datum used to calibrate the site levels, levels along all site boundaries, levels across the site at regular intervals and floor levels of adjoining buildings where relevant. This is also to include (ii) full details of the proposed finished floor levels of all buildings and hard surfaces including the ground floor(s) in relation to existing ground levels.
The following information was submitted:
- Existing Topographical Survey. SJ Geomatics. (Dwg No. SJG4963, Sheets 5-14)
- SITE B EXTERNAL WORKS GENERAL ARRANGEMENT PLAN SHEET 1 (Dwg. No. C-0101, Rev. P01)
- SITE B EXTERNAL WORKS GENERAL ARRANGEMENT PLAN SHEET 2 (Dwg. No. C-0102, Rev. P01)
- S38 SURFACING AND KERBING SITE B (Dwg No. C-0154, Rev. P01)
- S38 AGREEMENT PLAN SITE B (Dwg No. C-0152, Rev. P02)
- S38 CONTOURS PLAN SITE B (Dwg. No. C-0156, Rev. P02)
- S38 SETTING OUT AND DIMENSION PLAN - SITE B SHEET 1 (Dwg No. C-0158, Rev. P01)
- S38 SETTING OUT AND DIMENSION PLAN - SITE B SHEET 2 (Dwg No. C-0159, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 1 (Dwg. No. C-0166, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 2 (Dwg. No. C-0167, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 3 (Dwg. No. C-0168, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 4 (Dwg. No. C-0169, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 5 (Dwg. No. C-0170, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 6 (Dwg. No. C-0171, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 7 (Dwg. No. C-0172, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 8 (Dwg. No. C-0173, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 9 (Dwg. No. C-0174, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 10 (Dwg. No. C-0175, Rev. P02)
- S38 ADOPTABLE ROAD AND SEWER LONG SECTIONS SITE B SHEET 11 (Dwg. No. C-0176, Rev. P02)
Upon full assessment of the submitted information, this is acceptable and hereby approved. Condition 11 can be discharged in FULL. The condition now becomes a Compliance condition as this requires that the development is carried out only in strict accordance with the proposed ground / site levels and finished floor levels approved under part (ii) of this condition. |