| 1. | Condition 4 of pp. 06/24/1000/F requires the submission of a Noise and Dust Management Plan/Scheme to include the following:
1. Communication with neighbours before and during works.
2. Contact arrangements by which residents can raise any concerns and, issues.
3. The mechanism for investigation and responding to residents' concerns and complaints
4. Management arrangements to be put in place to minimise noise and dust (including staff training such as toolbox talks).
5. Hours during which noisy and potentially dusty activities will take place.
6. Measures to control loud radios on site.
7. Measures to be taken to ensure noisy activities take place away from residential premises where possible such as a separate compound for cutting and grinding activities.
8. Measures to control dust from excavation, wetting of soil; dust netting and loading and transportation of soil such as minimising drop heights, sheeting of vehicles.
9. Measures to control dust from soil stockpiles such as sheeting, making sure that stockpiles exist for the shortest possible time and locating stockpiles away from residential premises.
10. Measures to control dust from vehicle movements such as site speed limits, cleaning of site roads and wetting of vehicle routes in dry weather.
11. Measures to minimise dust generating activities on windy and dry days
12. Measures to control smoke from burning activities.
The following information was submitted:
- Noise & Dust Management Plan. Crofton Interiors. J455 East Norfolk Sixth Form College. Dated 20.05.2026.
Upon full assessment of the submitted details, the Noise and Dust Management Plan is considered acceptable and is hereby approved. The approved plan shall remain in place and be implemented throughout each phase of the development. |