No.Condition Text
1.Condition 11 requires details of the foul water drainage scheme to be submitted to and approved in writing by the Local Planning Authority and that the approved foul drainage scheme is implemented prior to the first use of the construction. The application is supported by the following documentation: 79505-WSP-XX-ZZ-DR-CV-0501 C06 - Proposed Foul and Surface Water Drainage Sheet 1 of 3 - Prepared by WSP - Dated May 24 79505-WSP-XX-ZZ-DR-CV-0502 C08 - Proposed Foul and Surface Water Drainage Sheet 2 of 3 - Prepared by WSP - Dated May 24 79505-WSP-XX-ZZ-DR-CV-0503 C08 - Proposed Foul and Surface Water Drainage Sheet 3 of 3 - Prepared by WSP - Dated May 24 Letter from Anglian Water, Application Reference: ALD-0110667 - Dated 3rd June 2021 Letter from Anglian Water, Application Reference: ALD-0157082 - Dated 13th December 2022 The submitted details are acceptable and are hereby approved and the condition is discharged in FULL.