| No. | Condition Text |
|---|---|
| 1. | Condition 16 of pp 06/20/0156/O required details of a construction management plan to be submitted to and approved by the local planning authority. The following information was submitted: Construction Method Statement Construction Management Plan (CMP) Revision A - Dated May 2025 - Prepared by Denbury Homes Construction Method Statement Construction Management Plan (CMP) APPENDIX C - Dated May 2025 - Prepared by Denbury Homes Construction Management Plan Appendix B - Drawing No.CMP1 - Revision D - Dated Nov 2024 - Prepared by Denbury Homes Upon full assessment of the submitted material supporting the application, considering all material considerations, the details are acceptable, and the condition is discharged in PART. Discharge in PART is only possible as the construction of the development must adhere to the construction management plan throughout the cycle of all construction stages from initial commencement. |