| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the following revised plan received by the Local Planning Authority on 25 February 2025:
-Plan no. 1726-CAM-XX-XX-DR-A-PL01 revision B, entitled Site Location Plan and Site Plan, dated 24 February 2025
And in accordance with the following revised plan received by the Local Planning Authority on 22 April 2025
- Plan no. 1726-CAM-XX-XX-DR-A-PL03 revision E, entitled Floor Plans and Elevations as Proposed, dated 22 April 2025
The reason for the condition is:-
For the avoidance of doubt of what has been approved and in the interests of proper planning. |
| 3. | Construction work shall not take place outside the following hours:-
07:30 to 18:30 Mondays
07:30 to 18:30 Tuesdays
07:30 to 18:30 Wednesdays
07:30 to 18:30 Thursdays
07:30 to 18:30 Fridays
08:30 to 13:30 Saturdays
and no work shall take place on Sundays or Bank Holidays.
(These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property)
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 4. | Asbestos Note:
The developer is reminded that prior to any refurbishment commencing on site the building/s to be refurbished are required to be surveyed for the presence of asbestos containing materials in accordance with the Control of Asbestos Regulations 2012. Any asbestos containing materials which are identified shall be managed or removed in accordance with the above regulations and waste regulations. Failure to comply with these regulations could result in prosecution by the relevant authority.
The uncontrolled refurbishment of buildings could result in the contamination of soils on site and in the vicinity of the demolition. This could cause the investigation of the site under Part 2A of the Environmental Protection Act 1990, which may result in the determining of the site as Contaminated Land.
For further help and advice in respect of asbestos removal the applicant/agent is advised to contact the Health and Safety Executive (HSE) (www.hse.gov.uk/asbestos) |
| 5. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |