1.The development must be completed within a period of 3 years starting with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of paragraph MA(2) (5) of Schedule 2 Part 3 Class MA of The Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended).
2.The development shall be carried out in accordance with the following revised plans received by the Local Planning Authority on the 17th September 2024: - Site Location Plan, Block Plan, Proposed Floor Plans and elevations; drawing reference: 1925/1 Rev.A The reason for the condition is:- For the avoidance of doubt of what has been approved and in the interests of proper planning.
3.The dwelling/s shall be constructed so as to provide sound attenuation against external noise and ensure internal sound levels no greater than: a) 35dB LAeq (16 hour) in the main living rooms of the dwelling(s) (for daytime and evening use); and b) 30dB LAeq (8 hour)/45dB LAmax (fast) in the bedrooms of the dwelling(s) (for night-time use) in line with World Health Organisation guidance, with windows shut and other means of ventilation provided. The reason for the condition is:- To ensure adequate living conditions for future occupiers and to World Health Organisation guidance levels.
4.NOTES - Please read the following notes carefully:- Asbestos Note: The developer is reminded that prior to any refurbishment commencing on site the building/s to be refurbished are required to be surveyed for the presence of asbestos containing materials in accordance with the Control of Asbestos Regulations 2012. Any asbestos containing materials which are identified shall be managed or removed in accordance with the above regulations and waste regulations. Failure to comply with these regulations could result in prosecution by the relevant authority. The uncontrolled refurbishment of buildings could result in the contamination of soils on site and in the vicinity of the demolition. This could cause the investigation of the site under Part 2A of the Environmental Protection Act 1990, which may result in the determining of the site as Contaminated Land. For further help and advice in respect of asbestos removal the applicant/agent is advised to contact the Health and Safety Executive (HSE) on 0845 345 0055 (www.hse.gov.uk/asbestos) INF09: Contamination Disclaimer NOTE: The responsibility for the safe development and secure occupancy of the site rests with the developer. The local planning authority has determined the application on the basis of the information available to it, but this does not mean that the land is free from contamination, or that the land could not be declared Contaminated Land in future. Hours of Work: Due to the close proximity of other residential dwellings and businesses, the hours of any construction or refurbishment works should be restricted to reduce the likelihood of noise disturbance to: 0730 hours to 1830 hours Monday to Friday 0830 hours to 1330 hours Saturdays No work on Sundays or Bank Holidays.