| No. | Condition Text |
|---|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the following plans received by the Local Planning Authority on the 17th June 2024: - Drawing No. 1 of 3 Elevations, Scale 1:100 - Drawing No. 2 of 3 FHI Sash Window Profile, Scale 1:2, and 1:10 - Drawing No. 3 of 3 Location and Site Map, Scale 1:500, 1:1250 The reason for the condition is:- For the avoidance of doubt. |
| 3. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |