No. | Condition Text |
---|
1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
2. | The development shall be carried out in accordance with the following plans received by the Local Planning Authority:
- Site Location Plan scale 1:1250 dated 29 May 2024
- Proposed Floor Plans; drawing reference: 3676.0424GY Rev B Sheet No. 2
The reason for the condition is:- For the avoidance of doubt of what has been approved and in the interests of proper planning. |
3. | The accommodation hereby approved shall only be used for temporary sleeping accommodation for the purpose of holiday, leisure, recreation, business or other travel and shall not be used at any time as a person's sole or principal residence. The applicant shall maintain a logbook detailing visitors staying at the premises and the period of time for which they are staying. The logbook shall be completed for the duration of the use of the premises as short term accommodation, and shall be made available for officers from the Local Planning Authority to view at all times.
The reason for the condition is :- To ensure the accommodation hereby approved is not used as permanent residential accommodation in accordance with policy L2 from the adopted Great Yarmouth Local Plan Part 2 (2021). |
4. | No use of the accommodation hereby approved shall take place until details of how the property will achieve a water consumption rate of no more than 110 litres/person/day has been first submitted to and approved in writing by the Local Planning Authority. All required water conservation measures within the approved details shall thereafter be installed and maintained to achieve this agreed rate prior to the first use of the accommodation to ensure the required water consumption is not exceeded for the lifetime of the development.
The reason for the condition is: - In the interests of promoting and securing water efficiency improvements to a higher standard than Building Regulations minimum standards require, to accord with adopted Local Plan Part 2 policy E7.
Note to applicant - The imposition of this planning condition requires the development to achieve a higher standard of construction than the current minimum national requirement through Building Regulations. This requires you / the Developer to ensure that the standard is adhered to when seeking Building Regulations Completion Notice approval (whether using local authority inspectors or third party approved inspectors). |
5. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner.
It is confirmed that this shadow HRA submitted by the applicant has been assessed as being suitable for the Borough Council as competent authority to use as the HRA record for the determination of the planning application, in accordance with the Conservation of Habitats and Species Regulations 2017.
In this instance the Borough Council has considered there is no likely significant effect on protected habitats arising solely from the development itself; and the development would contribute to the overall in-combination significant adverse effect identified by the Habitats Regulations Assessment Report for the Local Plan Core Strategy, but this effect can be adequately mitigated by the Habitats Monitoring and Mitigation Strategy; and that Strategy requires a payment of £221.17 per each additional dwelling equivalent (a total of £663.51) towards the monitoring and mitigation provided through that Strategy and this was paid on the 31st March 2025. |