| 2. | The development shall be carried out in accordance with the following plans:
- Unreferenced, undated and untitled plan (submitted as Site Location Plan) received by the Local Planning Authority on 31st July 2023.
- Unreferenced, undated and untitled plan (submitted as Block Plan of site) received by the Local Planning Authority on 31st July 2023.
- Plan No. 2681 / 3878 revision 1 Sheet 2 of 7, entitled Proposed Loft conversion (submitted as proposed ground floor floor plan), dated June 2023, received by the Local Planning Authority on 21st November 2023
- Plan No. 2681 / 3878 revision 1 Sheet 2 of 7, entitled Proposed Loft conversion (submitted as roof plan), dated June 2023, received by the Local Planning Authority on 21st November 2023
- Plan No. 2681 / 3878 revision 1 Sheet 4 of 7, entitled Proposed Loft conversion (submitted as loft floor construction plan), dated June 2023, received by the Local Planning Authority on 21st November 2023
- Plan No. 2681 / 3878 revision 1 Sheet 5 of 7, entitled Proposed Loft conversion (submitted as section plans), dated June 2023, received by the Local Planning Authority on 21st November 2023
The reason for the condition is:-
For the avoidance of doubt. |