| 1. | Condition 23 of 06/21/0415/F states:
"No works of construction of the road in the area referred to as 'Proposed road construction' shown on the Proposed Site Layout drawing ref: 003 Revision P05 shall take place until precise details of the following designs have first been submitted to and approved in writing by the Local Planning Authority:
i. Construction details of the road with a permanent continuous 3.0m wide footpath and shared cycleway along one side of the new road;
ii. Details of a temporary safe pedestrian route alongside the road for use until such time as the path is provided;
iii. Details of a phasing plan for footpath provision;
iv. Details to show how provision will be made to enable future footpath links along South Denes Road to connect with the application site; and
v. Details to show how provision will be made to enable future public transport connections into the site; and,
vi. A phasing plan or timetable for the provision of the road and permanent shared footpath facility, coincident with future developments within the application site undertaken pursuant to the development works approved within this permission.
Thereafter, the proposed road construction shall be carried out in accordance with the approved details including the provision of the footpath facilities to the timescale or phasing agreed therein.
The reason for the condition is :-
In the interests of highways safety, to ensure that highways access is maintained to a safe standard and that future access is constructed to appropriate standards."
The requirement to provide submitted details for Condition 23 has been fully discharged. Sufficient information to discharge the condition has been submitted and is approved. The submitted details address policies CS14, CS16 and GY10 and are considered acceptable.
The development must be undertaken in accordance with the following details:
- Letter dated 21 November 2022, ref: CES/PU6277/DC/Con23;
- 79505-WSP-XX-ZZ-DR-GA-001 rev P05 - General Arrangement Plan;
- 79505-WSP-XX-ZZ-DR-SD-0001 rev T01 - Typical Cross Sections;
- NCD1100-20 Revision B: Standard construction details - Kerbs, footways and paved areas;
- NCD1100-02 Revision B: Kerbs, Footways and Paved Areas Kerbs Full Depth;
- NCD1100-21: Kerbs, Footways, Pedestrian and Cycle Crossing Points Typical Details;
- NCD1100-01: Kerbs, Footways and Paved Areas Concrete Kerb Types;
- 79505-WSP-XX-ZZ-DR-LA-0001 Revision P02 - Ecology Enhancement and Landscape Proposals (Public Sector Funded Work) Sheet 1;
- 79505-WSP-XX-ZZ-DR-LA-0002 Revision P02 - Ecology Enhancement and Landscape Proposals (Public Sector Funded Work) Sheet 2; and,
- Email from Kate Dinis received 05 June 2023 13:41 confirming the road and highway infrastructure designs have been proposed in accordance with the Norfolk County Council Highways standards for adoption, and no further updates to drawings would be required for this condition application.
INFORMATIVE NOTES TO APPLICANT AND DEVELOPER:
The applicants and developers of future phases of the wider Operations and Maintenance Campus are reminded that their phases of development will be required to provide footpaths across their site frontages and connections to the road hereby approved, as part of their developments, and this would be required through any permission that is granted for any subsequent phase(s). |