Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is:- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the following plan: Drawing No. GYLH-CF-ZZ-XX-DR-A-0500 Plant Room Demolition Plan and Elevation The reason for the condition is:- For the avoidance of doubt.
3.In the event that contamination that was not previously identified is found at any time when carrying out the approved development, it must be reported in writing immediately to the Local Planning Authority. All development shall cease and shall not recommence until: 1) a report has been submitted and agreed in writing by the Local Planning Authority which includes results of an investigation and risk assessment together with proposed remediation scheme to deal with the risk identified and 2) the agreed remediation scheme has been carried out and a validation report demonstrating its effectiveness has been approved in writing by the Local Planning Authority. The reason for the condition is:- To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
4.NOTES - Please read the following notes carefully:- The site will potentially generate a significant amount of dust during the demolition process; therefore, the following measures should be employed: · An adequate supply of water shall be available for suppressing dust · Mechanical cutting equipment with integral dust suppression should be used · There shall be no burning of any materials on site, or burial of asbestos, which should instead be removed by an EA licenced waste carrier, and the waste transfer notes retained as evidence.
5.NOTES - Please read the following notes carefully:- Hours of work - Due to the proximity of other residential dwellings and businesses, the hours of any construction or refurbishment works should be restricted to: · 0730 hours to 1830 hours Monday to Friday · 0830 hours to 1330 hours Saturdays · No work on Sundays or Bank Holidays
6.NOTES - Please read the following notes carefully:- Asbestos - The developer is reminded that prior to any refurbishment commencing on site the building/s to be refurbished are required to be surveyed for the presence of asbestos containing materials in accordance with the Control of Asbestos Regulations 2012. Any asbestos containing materials which are identified shall be managed or removed in accordance with the above regulations and waste regulations. Failure to comply with these regulations could result in prosecution by the relevant authority. The uncontrolled refurbishment of buildings could result in the contamination of soils on site and in the vicinity of the demolition. This could cause the investigation of the site under Part 2A of the Environmental Protection Act 1990, which may result in the determining of the site as Contaminated Land. For further help and advice in respect of asbestos removal the applicant/agent is advised to contact the Health and Safety Executive (HSE) on 0845 345 0055 (www.hse.gov.uk/asbestos)
7.NOTES - Please read the following notes carefully:- This proposal involves works adjacent to the public highway. It is an OFFENCE to carry out any works that may affect the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. Please note that it is the Applicants' responsibility to ensure that, in addition to planning permission, any necessary consents or approvals under the Highways Act 1980 and the New Roads and Street Works Act 1991 are also obtained from the County Council. Please contact the Area Street Works Co-ordinator, email: streetworks.north@norfolk.gov.uk