| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the following revised plans received by the Local Planning Authority on 22nd August 2022:
- Site Location Plan 8247 P01
- Proposed Site Block Plan 8247 P.21 Rev #
- Proposed Site Block Plan 8247 P.21 Rev A
- Proposed Modular Unit Floor Plan and Elevations 8247 P.23
- Flood Risk Assessment July 2021 Ref: 2753/RE/07-21/01
The reason for the condition is:-
For the avoidance of doubt. |
| 3. | The materials to be used in the external walls and roof of the development hereby permitted shall match those stated in the application form and plans.
The reason for the condition is :-
In the interests of the visual amenities of the area. |
| 4. | The development hereby permitted shall have a ground floor level set at minimum of 1.45mAOD
Reason: Given the site location within an area at risk of tidal flooding |
| 5. | The flood warning and evacuation strategy, including information regarding the availability of the Environment Agency's Flood Warnings Service, shall be made available to future occupiers of the site.
The reason for the condition is :-
In accordance with the recommendations of the flood risk assessment, to minimise the risk to the occupants in the event of flooding. |
| 6. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |