| No. | Condition Text |
|---|
| 1. | The development must be begun not later than 3 years beginning with the date of this permission.
The reason for the condition is:-
Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the submitted site location plan; and revised floor plan and proposed elevational drawings received by the Local Planning Authority on 4th October 2022.
The reason for the condition is:-
For the avoidance of doubt. |
| 3. | The materials to be used in the external walls and roof of the development hereby permitted shall match those of the existing building or as otherwise specified in accordance with the details stated in the application form.
The reason for the condition is :-
In the interests of the visual amenities of the area. |
| 4. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria for domestic additions set out in adopted policies adopted policies A1, H9 from the Local Plan Part 2, and policy CS09 from the adopted Core Strategy. |
| 5. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |
| 6. | NOTES - Please read the following notes carefully:-
All necessary consents, including but not limited to Planning and Building Regulation consent, are in place before any work is undertaken at the property. The work must be carried out to good 'workmanship' standards, and it reflects current Building Regulation as a minimum. |
| 7. | The work should not obstruct or restrict, in any way, any easements or rights of way relating to sewage, water, electricity, gas or other utilities or means of access which do or may exist for the benefit of the land.
The reason for the condition is :-
To comply with Building Regulations 2000 (as amended by SI 2001/3335)
Building over sewers
H4. (1) The erection or extension of a building or work involving the underpinning of a building shall be carried out in a way that is not detrimental to the building or building extension or to the continued maintenance of the drain, sewer or disposal main.
(2) In this paragraph disposal main means any pipe, tunnel or conduit used for the conveyance of effluent to or from a sewage disposal works, which is not a public sewer.
Requirement H4 only applies to work carried out:
(a) over a drain, sewer or disposal main which is shown on any map of sewers; or
(b) on any site, or in such a manner as may result in interference with the use of, or obstruction of the access of any person to, any drain, sewere or disposal main which is shown on any map of sewers. |