Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is:- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the application form and approved plan, drawing reference: - Existing and Proposed plans - 1699/1 Received by the Local Planning Authority on 26th May 2022. The reason for the condition is:- For the avoidance of doubt.
3.Construction work shall not take place outside the following hours:- 07:30 to 18:30 Mondays 07:30 to 18:30 Tuesdays 07:30 to 18:30 Wednesdays 07:30 to 18:30 Thursdays 07:30 to 18:30 Fridays 08:30 to 13:30 Saturdays and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
4.The proposed window on the first floor rear elevation detailed on approved plan 1699/1 shall be fitted with obscure glass to a level equivalent to Pilkington Privacy Level 5 which shall be installed prior to the first occupation of the dwelling and this obscure glazing shall be retained thereafter in perpetuity. The reason for the condition is:- In the interests of the residential amenities of the occupiers of nearby properties.
5.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for domestic additions set out in adopted policy H9 of the Local Plan Part 2.
6.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner.
7.NOTES - Please read the following notes carefully:- The applicant must carry out an asbestos survey prior to demolition of the outbuilding to identify asbestos containing materials (ACMs). The developer has a legal duty to remove most ACMs before demolition and some ACMs must be removed by contractors licensed by the Health and Safety Executive (HSE). If at any stage during demolition asbestos is suspected the work should be stopped and the material investigated. Any cement bonded asbestos buildings must either be dismantled by licensed contractors or by non-licensed contractors who conform to a safe dismantling method. Broken or friable cement bonded asbestos sheeting should be removed by licensed contractors. Please outline the method you or your contractor will be following to dismantle the building prior to works commencing. All the resultant asbestos bonded sheets or other asbestos materials must be collected by a licensed waste carrier. Removal and disposal of asbestos containing materials must be carried out in accordance with HSE Approved Guidance Procedures.
8.NOTES - Please read the following notes carefully:- The site will potentially generate a significant amount of dust during the conversion process; therefore, the following measures should be employed: - - An adequate supply of water shall be available for suppressing dust; - Mechanical cutting equipment with integral dust suppression should be used; - There shall be no burning of any materials on site, or burial of asbestos, which should instead be removed by an EA licenced waste carrier, and the waste transfer notes retained as evidence.