1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is:- Required to be imposed pursuant to Section 18 of the Planning (Listed Building and Conservation Areas) Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the plans ASL-078 and detail drawing ASL-078/2-30 received by the Local Planning Authority on 07 March 2022. The reason for the condition is :- For the avoidance of doubt.
3.All original external and internal historic features, part of the special character of the heritage asset (including buttresses, brickwork, joinery of historic importance, etc) should be preserved and protected from any damage throughout the works. Any damaged fabric should be repaired in a like for like manner with relevant matching materials and techniques. The reason for the condition is:- To ensure that regard is paid to protecting the special architectural and historic interest and integrity of the building under Section 16 of the Planning (Listed Buildings and Conservation Areas) Act 1990.
4.All the new external and internal repair works to the retained fabric shall match the existing adjacent historic work with regard to the methods, materials, colour, texture and profile, unless agreed otherwise with the Local Planning Authority. Newly added brickwork should match the quality of the existing and should be laid in lime mortar. Any repointing should also be carried out in matching lime mortar. The reason for the condition is:- To ensure that the used materials and finishes are appropriate for the character and appearance of the Listed building.
5.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for work to listed buildings set out in saved Policies CS9, CS10 of the Core Strategy and A2 and E5 of the Local Plan Part 2.
6.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner.