| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is:-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the plans reference 6458:
TWGY-CF-A-ZZ-DR-A-0503 revision P3 site and highway circulation
TWGY-CF-A-ZZ-DR-A-0510 revision P4 block plan
TWGY-CF-A-ZZ-DR-A-0501 revision P4 ground plan
TWGY-CF-A-ZZ-DR-A-0512 revision P5 elevations
TWGY-CF-A-ZZ-DR-A-0505 revision P2 drainage strategy
received by the Local Planning Authority on 9 November 2021.
The reason for the condition is :- For the avoidance of doubt. |
| 3. | The premises shall not be open for business outside of the following hours:-
08.00 to 18.00 Mondays to Saturdays
10:00 to 16:00 on Sundays or Bank Holidays.
The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 4. | The northern access to the highway shown marked 'In' on the approved block plan within the submitted plans shall not be used for any purpose including construction traffic, until a scheme of signage for display within the site has first been submitted to and approved in writing by the Local Planning Authority to provide details which make it clear that this access shall not at any time be used for egress. The scheme shall receive the written approval of the local planning authority and be installed in accordance with that approval before the access is used, and shall thereafter be retained as such for the lifetime of the development.
The reason for the condition is :- in the interests of highway safety |
| 5. | Notwithstanding the provision of the Town and Country Planning (General Permitted Development) Order (2015), (or any Order revoking, amending or re-enacting that Order) no gates/bollard/chain/other means of obstruction shall be erected that might swing open outwards across the unadopted access road that is an extension to the adopted Thamesfield Way. Any gates etc shall swing into the site as shown on the submitted drawing.
The reason for the condition is: - In the interests of highway safety. |
| 6. | No development shall commence until a Phase 1 contamination report has first been carried out to assess whether the land is likely to be contaminated, and the results of the investigations submitted to and approved in writing by the Local Planning Authority.
The report to be submitted shall also include details of known previous uses and possible contamination arising from those uses. If contamination is suspected to exist, a Phase 2 site investigation is to be carried out to the satisfaction of the Local Planning Authority in consultation with the Environmental Health service. If the Phase 2 site investigation determines that the ground contains contaminants at unacceptable levels then the applicant is to submit a written strategy detailing how the site is to be remediated to a standard suitable for its proposed end-use. This subsequent report shall be submitted to and approved in writing by the Local Planning Authority before the commencement of construction works.
No buildings hereby permitted shall be occupied until the remediation works agreed within the scheme have first been carried out to the written satisfaction of the Local Planning Authority, following submission of a remediation verification report.
The reason for the condition is :-
To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 7. | In the event that contamination that was not previously identified is found at any time when carrying out the approved development, it must be reported in writing immediately to the Local Planning Authority. All development shall cease and shall not recommence until:
1) a report has been submitted and agreed in writing by the Local Planning Authority which includes results of an investigation and risk assessment together with proposed remediation scheme to deal with the risk identified and
2) the agreed remediation scheme has been carried out and a validation report demonstrating its effectiveness has been approved in writing by the Local Planning Authority.
The reason for the condition is :-
To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 8. | NOTES - Please read the following notes carefully:- Any signage within the site may require an advertisement consent application as well as a discharge of condition application. |
| 9. | NOTES - Please read the following notes carefully:- The use of this site is a mixed use proposal which includes a MOT testing station function a a principle activity which is a sui generis use, so a material change for example to vehicle repairs alone will require further planning permission. |
| 10. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria of CS6 and CS9 |
| 11. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |