1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the plans received by the Local Planning Authority on 26th July 2021 as listed below: Site Plan Received: 15th July 2021 Existing Floor Plans - Drawing No: RC01-P-01 Rev A1 Proposed Floor Plans - Drawing No: RC01-P-03 Rev A1 Block Plan - Drawing No: RC01-S-01 Rev A1 Existing Elevations - Drawing No: RC01-P-02 Rev A1 Proposed Elevations - Drawing No: RC01-P-04 Rev A1 The reason for the condition is:- For the avoidance of doubt.
3.The materials to be used in the development shall match those of the existing dwelling as specified on the application form received by the Local Planning Authority on 15th July 2021. The reason for the condition is :- For the avoidance of doubt.
4.No part of the proposed structure (to include foundations, fascia board/rainwater guttering) shall overhang or encroach upon highway land and no gate/door/ground floor window shall open outwards over the highway. The reason for the condition is :- In the interests of highway safety.
5.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for domestic additions set out in saved Policy HOU18 of the Great Yarmouth Borough-Wide Local Plan.
6.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner.
7.Informative This proposal involves excavations adjacent to the public highway. It is an OFFENCE to carry out any works that may affect the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. Please note that it is the Applicants' responsibility to ensure that, in addition to planning permission, any necessary consents or approvals under the Highways Act 1980 and the New Roads and Street Works Act 1991 are also obtained from the County Council. Please contact the Area Co-ordinator North; email streetworks.north@norfolk.gov.uk
8.Informative It is the Applicant's responsibility to clarify the boundary with the public highway. Private structures such as fences, or walls will not be permitted on highway land. The highway boundary may not match the applicant's title plan. For further details please contact the highway research team at highway.boundaries@norfolk.gov.uk