| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development hereby permitted shall be carried out in accordance with the following plans and details:
- Location Plan for Waterways SE CCTV Column (1 of 2) received by the Local Planning Authority on 16th February 2023;
- Location Plan for Waterways SE CCTV Column (2 of 2, with notation) received on 16/02/23;
- Applicant statement: 'Waterways SE CCTV Column', received 16/02/23;
- CCTV unit specification data sheet: RVX2 Combat Camera, received 04/02/22;
- Dwg: 28350-1 - Column elevation, received 18/02/22.
The reason for the condition is:-
For the avoidance of doubt and in the interests of preserving the character and setting of designated heritage assets. |
| 3. | The CCTV unit to be used on the column shall colour-match the column pole.
The reason for the condition is :-
In the interests of preserving the setting of designated heritage assets. |
| 4. | Any damage caused to the historic fabric or appearance of the Waterways park, structures or enclosures when undertaking this development shall be repaired and restored on a like-for-like basis within two months of the damage occurring.
The reason for the condition is :-
In the interests of visual amenity and protecting the character of designated heritage assets. |