Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the following plans and details: - Site Location Plan reference 8247: P01; - Floor plan reference 8247: P04 revision B; - Block plan and proposed elevations ref: P05 revision A; and, - Design and access statement and Flood risk assessment (where they reference the ongoing practices with regard to mitigation), all received by the Local Planning Authority on 21 July 2021. The reason for the condition is :- For the avoidance of doubt.
3.Development, including any demolition, shall not commence on site until a destructive asbestos survey of buildings to be demolished has first been submitted to and approved in writing by the Local Planning Authority. Development shall not be carried out other than in accordance with the approved details. The reason for the condition is:- Details are required to be submitted prior to commencement of works to ensure that risks from asbestos to the environment, future users of the land and neighbouring land are minimised, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other off-site receptors.
4.Development, including any demolition, shall not commence on site until a Phase 1 contamination report has first been carried out to assess whether the land is likely to be contaminated, and thereafter submitted to and approved in writing by the Local Planning Authority. The report shall also include details of known previous uses and possible contamination arising from those uses. If contamination is suspected to exist, a Phase 2 site investigation is to be carried out to the satisfaction of the Local Planning Authority in consultation with Environmental Health Officers. If the Phase 2 site investigation determines that the ground contains contaminants at unacceptable levels then the applicant is to submit a written strategy detailing how the site is to be remediated to a standard suitable for its proposed end-use to the Local Planning Authority in consultation with Environmental Health Officers. No buildings hereby permitted shall be occupied until the remediation works agreed within the scheme have been carried out to the satisfaction of the Local Planning Authority. The reason for the condition is :- To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
5.In the event that contamination that was not previously identified is found at any time when carrying out the approved development, it must be reported in writing immediately to the Local Planning Authority. All development shall cease and shall not recommence until: 1) a report has been submitted and agreed in writing by the Local Planning Authority which includes results of an investigation and risk assessment together with proposed remediation scheme to deal with the risk identified and 2) the agreed remediation scheme has been carried out and a validation report demonstrating its effectiveness has been approved in writing by the Local Planning Authority. The reason for the condition is :- To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
6.Construction work shall not take place outside the following hours:- 08:00 to 18:00 Mondays 08:00 to 18:00 Tuesdays 08:00 to 18:00 Wednesdays 08:00 to 18:00 Thursdays 08:00 to 18:00 Fridays 08:30 to 13:30 Saturdays and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
7.No part of the proposed structure (to include fascia board/rainwater guttering) shall overhang or encroach upon highway land and no gate/door/ground floor window shall open outwards over the highway. The reason for the condition is: - In the interests of highway safety.
8.There shall be no use of the development hereby permitted until the proposed access, on-site car and cycle parking and turning/drop-off area has first been laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use. The reason for the condition is: - To ensure the permanent availability of the parking/manoeuvring areas, in the interests of satisfactory development and highway safety.
9.It is the Applicant's responsibility to clarify the boundary with the public highway. Private structures such as fences, or walls will not be permitted on highway land. The highway boundary may not match the applicant's title plan. For further details please contact the highway research team at highway.boundaries@norfolk.gov.uk