Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be completed within a period of 3 years starting with the date prior approval is granted. The developer must notify the local planning authority of the completion of the development as soon as reasonably practicable after completion. The reason for the condition is :- To comply with the provisions of Class Q.
2.The development shall be carried out in full accordance with the following plans received by the Local Planning Authority on the 1st June 2021: - Location Plan - drawing ref: 21/033105/001. - Proposed Site Plan - ref: 21/033105/003. - Proposed Elevations - ref: 21/033105/109/C. - Proposed Ground Floor - ref: 21/033105/105/C. The reason for the condition is:- For the avoidance of doubt and to ensure the development is undertaken in accordance with the criteria of Class Q.
3.The new dwellinghouse created under Class Q is to remain in use as a dwellinghouse within the meaning of Class C3 of the Schedule to the 1987 Town and Country Planning Use Class Order (as amended) and for no other purpose, except to the extent that any other purpose is ancillary to the primary use as a dwellinghouse. The reason for the condition is :- To comply with the provisions of Class Q.
4.The area of the existing building labelled for demolition on the north elevation (as indicated on plan 21/033105/109/C received by the Local Planning Authority on the 1st June 2021) shall be demolished and all associated materials removed from site prior to the commencement of any works on the conversion of the agricultural building. The reason for the condition is :- To ensure the development is both visually appropriate and able to satisfy the Class Q requirements in respect of both satisfying the floorspace requirements and the requirement for undertaking demolition to the extent necessary for the conversion, and the requirement for provision of natural light to the habitable rooms shown in the approved plans.
5.In the event that contamination that was not previously identified is found at any time when carrying out the approved development, it must be reported in writing immediately to the Local Planning Authority. All development shall cease and shall not recommence until: 1) a report has been submitted and agreed in writing by the Local Planning Authority which includes results of an investigation and risk assessment together with proposed remediation scheme to deal with the risk identified and 2) the agreed remediation scheme has been carried out and a validation report demonstrating its effectiveness has been approved in writing by the Local Planning Authority. The reason for the condition is :- To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
6.Construction work shall not take place outside the following hours:- 08:00 to 18:00 Mondays 08:00 to 18:00 Tuesdays 08:00 to 18:00 Wednesdays 08:00 to 18:00 Thursdays 08:00 to 18:00 Fridays 08:30 to 13:30 Saturdays and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
7.NOTES - Please read the following notes carefully:- The applicant is reminded that, under the Wildlife and Countryside Act 1981, as amended (section 1), it is an offence to remove, damage or destroy the nest of any wild bird while the nest is in use or being built. Planning consent for a development does not provide a defense against prosecution under this act. While trees and scrub are likely to contain nesting birds between 1st March and 31st August inclusive buildings can also support nesting birds. If works occur during the nesting period a careful check of the building by a competent ecologist should be undertaken to assess the nesting bird activity on the site during this period and has shown it is absolutely certain that nesting birds are not present.
8.NOTES - Please read the following notes carefully:- Occasionally European protected species, such as bats, can be found during the course of the development. In the event that this occurs, it is advised that the developer stops work immediately and seeks the advice of a suitably qualified ecological consultant.