| No. | Condition Text |
|---|
| 1. | The requirement to provide written submission details for Condition 3 is discharged. The surface water drainage scheme 21st August 2020 prepared by Rossi Long (project reference PDC/201329 [Rev 00] received by the Local Planning Authority on the 17th February 2021 has been considered acceptable by the Local Planning Authority. The development shall take place in accordance with the approved details. |
| 2. | The requirement to provide written submission details for Condition 8 is discharged. The Hydrogeological Risk Assessment received by the Local Planning Authority on the 28th September 2022 has been deemed acceptable and contains sufficient information to discharge condition 8. The development shall take place in accordance with the approved details. |
| 3. | Condition 6 is partially discharged. The Hydrogeological Risk Assessment received by the Local Planning Authority on the 28th September 2022 has been deemed acceptable and contains sufficient information to discharge Part 1 and 2 of condition 6. The development shall be carried out in accordance with the approved details and recommendations contained within the report. Parts 3 and 4 of the condition cannot be discharged at this time and must remain until the Local Planning Authority has received and approved the final remediation strategy and validation report. |
| 4. | Condition 7 is NOT discharged. Insufficient information has been received to discharge the condition; in particular there has not been a verification report demonstrating completion of the remediation works submitted to the Council. Further detail is required for the condition to be discharged and this application is accordingly REFUSED. |
| 5. | Condition 9 is NOT discharged. Insufficient information has been received to discharge the condition; in particular, this condition relates to contamination found during construction, works have yet to commence and this condition must stay in place to safeguard against any future discovery of contamination. Further detail is required for the condition to be discharged and this application is accordingly REFUSED. |
| 6. | Condition 10 is NOT discharged. The surface water drainage scheme approved under the discharge of Condition 3 precludes the use of infiltration. This condition reiterates this approach in the interests of avoiding contamination of the water course and no information to suggest otherwise than this condition should remain in place has been received. This application is accordingly REFUSED. |
| 7. | Condition 11 is NOT discharged. No information has been submitted along with the application to demonstrate how, why and when piling would take place or any details to confirm that piling would not result in an unacceptable risk to groundwater. This condition cannot be discharged and this application is accordingly REFUSED. |
| 8. | Condition 13 is NOT discharged. The application is not supported by any additional information further than what was included in the Flood Risk Assessment submitted on the original application (06/19/0387/F). The condition cannot be discharged at this time as insufficient information has been submitted and this application is accordingly REFUSED. |
| 9. | Condition 14 is NOT discharged. The application is not supported by any additional information further than what was included in the Flood Risk Assessment submitted on the original application (06/19/0387/F). The condition cannot be discharged at this time as insufficient information has been submitted and this application is accordingly REFUSED. |
| 10. | Condition 16 is NOT discharged. The application is not supported by any additional information further than what was included on the approved plans on (06/19/0387/F) and as such fails to provide the detailed hard and soft landscaping scheme required by the condition. The condition cannot be discharged at this time as insufficient information has been submitted and this application is accordingly REFUSED. |
| 11. | Condition 17 is NOT discharged. The application is not supported by sufficient detail to determine the precise external materials, in particular there is no evidence of what the external cladding would be or any detail as to what brick is proposed. The condition cannot be discharged at this time as insufficient information has been submitted and this application is accordingly REFUSED. |