| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the following Drawings:-
ENV000382C-JBAB-DW4-_WP02-DR-PL-1000 - Site Location Plan
ENV000382C-JBAB-DW4-_WP02-DR-PL-1001 - General Arrangement Overview Plan
ENV000382C-JBAB-DW4-_WP02-DR-PL-1002- PO2 (revised 25.03.21) Working Area Plan
ENV000382C-JBAB-DW4-_WP02-DR-PL-1100 - General Arrangement Sheet (1 of 2)
ENV000382C-JBAB-DW4-_WP02-DR-PL-1101- General Arrangement Sheet (2 of 2)
ENV000382C-JBAB-DW4-_WP02-DR-PL-1300- Elevations/Sections Sheet (1 of 2)
ENV000382C-JBAB-DW4-_WP02-DR-PL-1301 - Elevations/Sections Sheet (2 of 2)
and supporting Documents ENV000382C-JBAB-ZZ-4_WP02-RP-C-0002_WP02 -Flood Risk Assessement
The reason for the condition is :- For the avoidanace of doubt and in accordance with submiited assessed details.. |
| 3. | If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until the developer has submitted a remediation strategy to the local planning authority detailing how this unsuspected contamination shall be dealt with and obtained written approval from the local planning authority. The remediation strategy shall be implemented as approved.
The reason for the condition is :- To protect and prevent the pollution of the water environment (particularly groundwater associated with the underlying Secondary and Principal Aquifers, from potential pollutants associated with current and previous land uses) in line with National Planning Policy Framework (NPPF; paragraphs 170 and 178), EU Water Framework Directive, Anglian River Basin Management Plan and Environment Agency Groundwater Protection Position Statements (2018).
National Planning Policy Framework (NPPF) paragraph 170 states that the planning system should contribute to and enhance the natural and local environment by preventing both new and existing development from contributing to or being put at unacceptable risk from, or being adversely affected by unacceptable levels of water pollution. Government policy also states that planning policies and decisions should also ensure that adequate site investigation information, prepared by a competent person, is presented (NPPF, paragraph 178).
|
| 4. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |
| 5. | This development involves work to the public highway that will require the approval of the County Council as Highway Authority. It is an OFFENCE to carry out any works within the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. Please note that it is the applicants' responsibility to ensure that, in addition to planning permission, any necessary consents or approvals under the Highways Act 1980 and the New Roads and Street Works Act 1991 are also obtained from the County Council. Advice on this matter can be obtained from the County Council's Area Managers based at (insert appropriate area contact details).
Public Utility apparatus may be affected by this proposal. Contact the appropriate utility service to reach agreement on any necessary alterations, which have to be carried out at the expense of the developer.
It is for the applicant's esponsibilty to clarify the boundary with the public highway.Private structures such as fences, or walls will not be permitted on highway land. The highway boundary may not match the applicants title plan.For further details please contact the highways research team at highways.boundaries@norfolk.gov.uk |