| No. | Condition Text |
|---|---|
| 1. | Condition 6 is DISCHARGED with regard to the information required before works, by the email from environmental health received 11 February 2021. Further information will be required as being submitted to fully discharge the condition including the validation of the remediation upon completion of the works. |