| No. | Condition Text |
|---|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is:- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the application form and plans and photos received by the Local Planning Authority on 9 November 2020 The reason for the condition is :- For the avoidance of doubt. |
| 3. | Before works commence on the roof further details of the following shall be submitted in written and drawn form to the local planning authority and approved by the Authority The stepped lead flashing with soakers will be employed where the existing roof abuts the 19th century part of the structure, including the lead code and means of fixing to the existing building. The Slate type, colour and slate size. The works shall proceed in accordance with the approved scheme. The reason for the condition is :- To ensure the works preserve and enhance the listed building. |
| 4. | Before works commence on the provision of the extract further details of the following shall be submitted in written and drawn form to the local planning authority and approved by the Authority: details of the extract fan location and termination The works shall proceed in accordance with the approved scheme. The reason for the condition is :- To ensure the works preserve and enhance the listed building |