| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the application forms and the following revised plan (Drawing ref: 1528/1 Rev.A) received by the Local Planning Authority on the 25th September 2020.
The reason for the condition is:-
For the avoidance of doubt. |
| 3. | Construction work shall not take place outside the following hours:-
08:00 to 18:00 Mondays
08:00 to 18:00 Tuesdays
08:00 to 18:00 Wednesdays
08:00 to 18:00 Thursdays
08:00 to 18:00 Fridays
08:30 to 13:30 Saturdays
and no work shall take place on Sundays or Bank Holidays.
(These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property)
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 4. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria set out in Core Policy CS09 from the adopted Core Strategy. |
| 5. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |
| 6. | NOTES - Please read the following notes carefully:-
The site is located within the SMP erosion lines for both the 2055 and 2105 epochs. The developer / owner should be aware of the longer term coastal change and potential erosion. |