| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2. | The development hereby permitted shall be carried out in accordance with the submitted application form and drawing numbers: MC02-L-01/001 Rev A1, MC02-P-01/001 Rev A1, MC02-P-01/002 Rev A1, MC02-P-02/001 Rev A1, MC02-P-02/002 Rev A1, MC02-P-03/001 Rev A1, MC02-P-04/001 Rev A1, MC02-P-05/001 Rev A1 and MC02-S-01/001 Rev A1 received on 17 August 2020 by the Local Planning Authority and shall be retained in the approved form thereafter. No material variation from these plans shall take place unless otherwise first agreed in writing with the Local Planning Authority.
The reason for the condition is :-
In order that the development hereby permitted shall be fully implemented in complete accordance with the approved plans and to accord with the Great Yarmouth Borough-Wide Local Plan. |
| 3. | Materials to be used in the construction of the external surfaces of the development other than those stated on the application form shall match the external materials used in the existing dwelling.
The reason for the condition is :-
In the interest of the character and amenity of the area in accordance with the Great Yarmouth Borough-Wide Local Plan. |
| 4. | The development (outbuildings and pool ) hereby permitted shall only be used for private domestic use in connection with the dwelling to which it relates. No business or commercial activity shall be carried on, within, or from the development hereby approved. The outbuildings and pool shall be retained as part of the main property and shall not be sold separately at any time.
The reason for this condtion is:-
In the interests of the residential amenities of the occupiers of adjacent property. |
| 5. | The floor levels of the proposed developments hereby permitted shall not be set lower than the existing levels of the existing dwelling and electrical sockets shall be raised to a safe internal level.
The reason for the condition is :-
In the interests of the flood prevention and residential amenities of the occupiers of nearby dwellings. |
| 6. | In the event that contamination that was not previously identified is found at any time when carrying out the approved development, it must be reported in writing immediately to the Local Planning Authority. All development shall cease and shall not recommence until:
1) a report has been submitted and agreed in writing by the Local Planning Authority which includes results of an investigation and risk assessment together with proposed remediation scheme to deal with the risk identified and
2) the agreed remediation scheme has been carried out and a validation report demonstrating its effectiveness has been approved in writing by the Local Planning Authority.
The reason for the condition is :-
To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 7. | Construction work shall not take place outside the following hours:-
08:00 to 18:00 Monday to Friday.
08:30 to 13:30 Saturday
No work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property).
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 8. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria for domestic additions set out in saved Policy HOU18 of the Great Yarmouth Borough-Wide Local Plan. |
| 9. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |
| 10. | NOTES - Please read the following notes carefully:-
The site will potentially generate a significant amount of dust during the construction process therefore, the following measures should be employed;
1. An adequate supply of water shall be available for suppressing dust.
2. Mechanical cutting equipment with integral dust suppression should be used.
3 There shall be no burning of nay materials on site. |