| No. | Condition Text |
|---|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is:- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the plan SJC P02 received by the Local Planning Authority on 7th October 2020. The reason for the condition is :- For the avoidance of doubt. |
| 3. | No work shall commence on any part of the new buildings construction that is above ground level until the exact types and colours of the materials have been submitted to and approved by the Local Planning Authority. The development shall be carried out using the agreed materials. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of the materials have not been submitted. |