1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development hereby permitted shall be carried out in accordance with the submitted application form, Design and Access Statement, Flood Risk Assessment Report 2534/RE/06-20/01 (dated June 2020) received on 15 July 2020 and revised drawing number: 2038-002 received on 9 October 2020 by the Local Planning Authority and shall be retained in the approved form thereafter. No material variation from these plans shall take place unless otherwise first agreed in writing with the Local Planning Authority. The reason for the condition is :- In order that the development hereby permitted shall be fully implemented in complete accordance with the approved plans and to accord with the Great Yarmouth Borough-Wide Local Plan.
3.Prior to the occupation/use of the development hereby permitted ,the standard flood evacuation plan, prevention and resilience and measures submitted in the Flood Risk Assessment Report 2534/RE/06-20/01 (dated June 2020) received on 29 July 2020 by the Local Planning Authority shall be implemented as follows: 1. Environmental Agency to issue a 12 hour notice before the issue of a flood warning for tidal events to the occupants . 2. Users of the premises must keep a Business Flood Plan, Flood Kit ,Water Entry and Exclusion Plan on site. 3. The emergency shut off of electricity, gas and water supply into the dwelling shall be implemented during a flood event. 4. Use of ceramic or concrete based internal flooring, flood proofing measures to be incorporated within the walls up to the flood level and the use of durable fittings such as plastic or stainless steel units. 5. All electrical sockets to be raised above the flood level 1.14 metres. The reason for the condition is :- In the interest of safety from flooding and the amenities of adjacent premises.
4.No gate(s) if installed shall open outwards over the highway. The reason for the condition is: - In the interests of highway safety.
5.Prior to the first use of the development hereby permitted the proposed access, on-site car and cycle parking and servicing/turning/waiting area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use. The reason for the condition is: - To ensure the permanent availability of the parking/manoeuvring areas, in the interests of satisfactory development and highway safety.
6.Construction work shall not take place outside the following hours:- 08:00 to 18:00 Monday to Friday, 08:30 to 13:30 Saturday No work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property). The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.