| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the plans, reference 1414/1141/2 and forms received by the Local Planning Authority on the 2nd August 2019.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | No development shall take place until the following information has been submitted to and approved in writing by the
Local Planning Authority:
(i) a full site survey showing:
the datum used to calibrate the site levels
levels along all site boundaries
levels across the site at regular intervals
floor levels of adjoining buildings
(ii) full details of the proposed finished floor levels of all buildings, ground levels and hard surfaces.
The development shall be carried out only in accordance with the approved details.
The reason for the condtions is:-
To ensure that the development takes place in the manner contemplated by the Local Planning Authority and to retain control over any significant changes in levels within the site. This is required to be a pre commencement condition as any proposed increases or reduction in site level must be known and agreed prior to commencement to prevent the need for reversal. |
| 4. | No work shall commence above slab level until the exact types and colours of the materials and boundary treatments have been submitted to and approved by the Local Planning Authority. The development shall be carried out using the agreed materials. The materials shall include roof tiles which offer bird and bat roosting opportunities. The boundary treatments shall have holes at ground level no less than 10cm x10cm in size at all boundaries to allow for the free passage of animals. These holes shall be retained in perpetuity.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of the materials have not been submitted. |
| 5. | No works shall commence on the site until such time as detailed plans of the roads, footways and foul and surface water drainage have been submitted to and approved in writing by the Local Planning Authority. All construction works shall be carried out in accordance with the approved plans
The reason for the condition is :-
This needs to be a pre-commencement condition to ensure fundamental elements of the development that cannot be retrospectively designed and built are planned for at the earliest possible stage in the development and therefore will not lead to expensive remedial action and adversely impact on the viability of the development. |
| 6. | Prior to the occupation of the final dwelling all works shall be carried out on roads/footways/foul and surface water sewers in accordance with the approved specification to the satisfaction of the Local Planning Authority.
The reason for the condition is :-
To ensure satisfactory development of the site and to ensure estate roads are constructed to a standard suitable for adoption as public highway. |
| 7. | Before any dwelling unit is first occupied the road(s)/footway(s) shall be constructed to binder course surfacing level from the dwelling unit to the adjoining County road in accordance with the details to be approved in writing by the Local Planning Authority.
The reason for the condition is :-
To ensure satisfactory development of the site. |
| 8. | Prior to the first occupation of the development hereby permitted visibility
splays measuring 2.4 x 43 metres shall be provided to each side of the access where it meets the highway. The splay(s) shall thereafter be maintained at all times free from any obstruction exceeding 0.225 metres above the level of the adjacent highway carriageway.
The reason for the condition is :-
In the interests of highway safety in accordance with the principles of the NPPF. |
| 9. | Prior to the first occupation/use of the development hereby permitted the proposed access, on-site car parking and turning area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use.
The reason for the condition is :-
To ensure the permanent availability of the parking/ manoeuvring areas, in the interests of satisfactory development and highway safety. |
| 10. | Development shall not commence until a scheme detailing provision for on-site parking for construction workers for the duration of the construction period has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented throughout the construction period.
The reason for the condition is :-
To ensure adequate off-street parking during construction in the interests of highway safety. This needs to be a pre-commencement condition as it deals with the construction period of the development. |
| 11. | Construction work shall not take place outside the following hours:-
08:00 to 18:00 Monday
08:00 to 18:00 Tuesday
08:00 to 18:00 Wednesday
08:00 to 18:00 Thursday
08:00 to 18:00 Friday
08:30 to 13:30 Saturday
and no work shall take place on Sundays or Bank Holidays.
(These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property)
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 12. | Prior to the commencement of the development and to the satisfaction of the Environmental Services Manager, a Phase 1 contamination report shall be carried out to assess whether the land is likely to be contaminated. The report shall also include details of known previous uses and possible contamination arising from those uses. If contamination is suspected to exist, a Phase 2 site investigation is to be carried out to the satisfaction of the Environmental Services Manager. If the Phase 2 site investigation determines that the ground contains contaminants at unacceptable levels then the applicant is to submit a written strategy detailing how the site is to be remediated to a standard suitable for its proposed end-use to the Environmental Services Manager. No buildings hereby permitted shall be occupied until the remediation works agreed within the scheme have been carried out to the satisfaction of the Local Planning Authority.
The reason for the condition is :-
To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 13. | In the event that contamination that was not previously identified is found at any time when carrying out the approved development, it must be reported in writing immediately to the Local Planning Authority. All development shall cease and shall not recommence until:
1) a report has been submitted and agreed in writing by the Local Planning Authority which includes results of an investigation and risk assessment together with proposed remediation scheme to deal with the risk identified and
2) the agreed remediation scheme has been carried out and a validation report demonstrating its effectiveness has been approved in writing by the Local Planning Authority.
The reason for the condition is :-
To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 14. | A) No development shall take place until an archaeological written scheme of investigation has been submitted to and approved by the local planning authority in writing. The scheme shall include an assessment of significance and research questions; and 1) The programme and methodology of site investigation and recording, 2) The programme for post investigation assessment, 3) Provision to be made for analysis of the site investigation and recording, 4) Provision to be made for publication and dissemination of the analysis and records of the site investigation, 5) Provision to be made for archive deposition of the analysis and records of the site investigation and 6) Nomination of a competent person or persons/organization to undertake the works set out within the written scheme of investigation.
and,
B) No development shall take place other than in accordance with the written scheme of investigation approved under condition (A).
and,
C) The development shall not be occupied until the site investigation and post investigation assessment has been completed in accordance with the programme set out in the archaeological written scheme of investigation approved under condition (A) and the provision to be made for analysis, publication and dissemination of results and archive deposition has been secured.
The reason for the condition is: -
In accordance with National Planning Policy Framework 2019 paragraphs 199 and 189. |
| 15. | Prior to occupation of the development hereby approved details of landscaping and biodiversity enhancements shall be submitted to and approved by the Local Planning Authority. The landscaping and biodiversity improvements shall be carried out in accordance with the details approved prior to occupation of any of the dwellings and shall remain as such thereafter.
The reason for the condition is:-
In the interests of the visual amenities of the locality. |
| 16. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal complies with the aims of Policies CS2, CS3, CS9 CS11 and CS14 of the Great Yarmouth Core Strategy. |
| 17. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |
| 18. | INFORMATIVE - Please note that the site will potentially generate a significant amount of dust during the construction process; therefore, the following measures should be employed: -
-An adequate supply of water shall be available for suppressing dust;
-Mechanical cutting equipment with integral dust suppression should be used;
-There shall be no burning of any materials on site. |
| 19. | INFORMATIVE - Please note it is an OFFENCE to carry out any works within the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. This development involves work to the public highway that can only be undertaken within the scope of a Legal Agreement between the applicant and the County Council. Please note that it is the applicant's responsibility to ensure that, in addition to planning permission, any necessary Agreements under the Highways Act 1980 are also obtained. Advice on this matter can be obtained from the County Council's Highways Development Management Group based at County Hall in Norwich.
Public Utility apparatus may be affected by this proposal. Contact the appropriate utility service to reach agreement on any necessary alterations, which have to be carried out at the expense of the developer.
If required, street furniture will need to be repositioned at the applicant's expense. |
| 20. | NOTES - Please read the following notes carefully:-
Great Yarmouth Borough Council has a duty to ensure that roads and streets within the Borough are properly named and that the properties fronting onto them are appropriately numbered. Therefore it is essential that once planning permission has been granted, and prior to the completion of development, the developer/owner applies for an official address. This Authority has adopted the legislation set out in sections 17, 18 and 19 of The Public Health Act 1925. In common with most neighbouring local authorities, Great Yarmouth Borough Council is introducing charging for the street naming and numbering of new developments from the 1st January 2020. Charges and more information can be seen on the Council's website here: https://www.great-yarmouth.gov.uk/street-naming-numbering |