1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the application form and approved plan (Drawing reference 646.2) received by the Local Planning Authority on 19 July 2019 and the revised plan received by the Local Planning Authority (drawing reference: 646.2a) on the 14 October 2019. The reason for the condition is :- For the avoidance of doubt.
3.No work shall commence until the exact types and colours of the materials have been submitted to and approved by the Local Planning Authority. The development shall be carried out using the agreed materials. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of the materials have not been submitted.
4.Construction work shall not take place outside the following hours:- 08:00 to 18:00 Monday to Friday 08:30 to 13:30 Saturday and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
5.The site will potentially generate a significant amount of dust during the demolition and construction processes; therefore, the following measures should be employed: -An adequate supply of water shall be available for suppressing dust; -Mechanical cutting equipment with integral dust suppression should be used; -There shall be no burning of materials on site, which instead should be removed by an EA licenced waste carrier, and the waste transfer notes retained as evidence. The reason for the condition is :- To ensure the works can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
6.Prior to the commencement of the development and to the satisfaction of the Environmental Services Manager, a Phase 1 contamination report shall be carried out to assess whether the land is likely to be contaminated. The report shall also include details of known previous uses and possible contamination arising from those uses. If contamination is suspected to exist, a Phase 2 site investigation is to be carried out to the satisfaction of the Environmental Services Manager. If the Phase 2 site investigation determines that the ground contains contaminants at unacceptable levels then the applicant is to submit a written strategy detailing how the site is to be remediated to a standard suitable for its proposed end-use to the Environmental Services Manager. No buildings hereby permitted shall be occupied until the remediation works agreed within the scheme have been carried out to the satisfaction of the Local Planning Authority. The reason for the condition is :- To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. (Note: the applicant is strongly advised to contact Environmental Health at an early stage.)
7.In the event that contamination that was not previously identified is found at any time when carrying out the approved development, it must be reported in writing immediately to the Local Planning Authority. All development shall cease and shall not recommence until: 1) a report has been submitted and agreed in writing by the Local Planning Authority which includes results of an investigation and risk assessment together with proposed remediation scheme to deal with the risk identified and 2) the agreed remediation scheme has been carried out and a validation report demonstrating its effectiveness has been approved in writing by the Local Planning Authority. The reason for the condition is :- To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
8.Prior to the first occupation/use of the development hereby permitted the proposed access and on-site car parking area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use. The reason for the condition is :- To ensure the permanent availability of the parking/ manoeuvring areas, in the interests of satisfactory development and highway safety.
9.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking and re-enacting the order) no extensions shall be built or windows inserted into the walls or roof of the building without the prior consent of the Local Planning Authority. The reason for the condition is:- In the interests of the residential amenities of the occupiers of the adjacent property.
10.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria outlined in policies CS2, CS3 and CS9 of the adopted Core Strategy.
11.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner.