| No. | Condition Text |
|---|
| 1. | Application for approval of reserved matters must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun not later than the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved.
The reason for this condition:-
The time limit condition is imposed in order to comply with the requirements of Section 92 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | No development whatsoever shall take place until full details of the siting, design and external appearance (herein after referred to as the reserved matters) have been submitted to and approved by the Local Planning Authority and the development shall be carried out strictly in accordance with such approved details.
The reason for the condition is:-
Such details have not been submitted as part of this application. |
| 3. | Construction work shall not take place outside the following hours:-
08:00 to 18:00 Monday to Friday
08:30 to 13:30 Saturday
and no work shall take place on Sundays or Bank Holidays.
(These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property)
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 4. | Prior to the first occupation of the development hereby permitted the vehicular access shall be constructed in accordance with a detailed scheme to be agreed in writing with the Local Planning Authority in accordance with the highways specification (TRAD 5) and thereafter retained at the position shown on the approved plan. Arrangement shall be made for surface water drainage to be intercepted and disposal of separately so that it does not discharge from or onto the highway.
The reason for the condition is :-
To ensure construction of a satisfactory access and to avoid carriage of extraneous material or surface water from or onto the highway in the interests of highway safety. |
| 5. | Notwithstanding the provision of the Town and Country Planning (General Permitted Development) Order (2015), (or any Order revoking, amending or re-enacting that Order) no gates/bollard/chain/other means of obstruction shall be erected across the approved access unless details have first been submitted to and approved in writing by the Local Planning Authority.
The reason for the condition is :-
In the interests of highway safety. |
| 6. | Prior to the first occupation/use of the development hereby permitted a 2.4 metre wide parallel visibility splay (as measured back from the near edge if the adjacent highway carriageway) shall be provided across the whole of the site's roadside frontage.
The splay(s) shall thereafter be maintained at all times free from any obstruction exceeding 0.225/0.6/1.05 metres above the level of the adjacent highway carriageway.
The reason for the condition is :-
In the interests of highway safety in accordance with the principles of the NPPF. |
| 7. | This development involves works within the public highway that can only be carried out by Norfolk County Council as Highway Authority unless otherwise agreed in writing.
It is an OFFENCE to carry out any works within the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. Please note that it is the applicant's responsibility to ensure that, in addition to planning permission, any necessary consents or approvals under the Highways Act 1980 and the New Roads and Street Works Act 1991 are also obtained from the County Council. Advice on this matter can be obtained from the County Council's Highway Design and Development Group. Please contact Stuart French on 01603 638070.
If required, street furniture will need to be repositioned at the applicant's expense.
Public Utility apparatus may be affected by this proposal. Contact the appropriate utility service to reach agreement on any necessary alterations, which have to be carried out at the expense of the developer. |
| 8. | Please be aware it is the applicants responsibility to clarify the boundary with the public highway. Private structures such as fences or walls will not be permitted on highway land. The highway boundary may not match the applicants title plan. Please contact the highway research team at highway.boundaries@norfolk.gov.uk for further details. |
| 9. | No work shall commence until the exact types and colours of the materials have been submitted to and approved by the Local Planning Authority. The development shall be carried out using the agreed materials.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of the materials have not been submitted. |
| 10. | No development shall take place until the following information has been submitted to and approved in writing by the
Local Planning Authority:
(i) a full site survey showing:
the datum used to calibrate the site levels
levels along all site boundaries
levels across the site at regular intervals
floor levels of adjoining buildings
(ii) full details of the proposed finished floor levels of all buildings and hard surfaces.
The development shall be carried out only in accordance with the approved details.
No development shall take place until full details of the finished levels, above ordnance datum, of the ground floor(s) of the proposed building(s), in relation to existing ground levels have been submitted to and approved by the Local Planning Authority. The development shall be carried out in strict accordance with the levels approved.
The reason for the condtions is:-
To ensure that the development takes place in the manner contemplated by the Local Planning Authority and to retain control over any significant changes in levels within the site. |
| 11. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new housing development set out in saved Policy HOU7 of the Great Yarmouth Borough-Wide Local Plan. |
| 12. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |