| No. | Condition Text |
|---|
| 1. | The development hereby permitted shall be carried out entirely in accordance with the details shown on the application forms, design and access statement and plans received by the Local Planning Authority on 13th February 2013 and notwithstanding the Town and Country Uses Classes Order the building shall be for a storage and office use only in accordance with the approved layout and plans and shall not be used for any other purpose (including any other purpose within the Town and Country Planning (Use Classes) Order 1987, or in any provision equivalent to that class in any statutory instrument revoking and re-enacting that order with or without modification)
The reason for the condition is :-
In accordance with the terms of the aplication and submitted details. |
| 2. | Prior to commencement of the use hereby permitted any access gate(s), bollard,chain or other means of obstruction shall be hung to open inwards and shall be set back a minimum distance of 5 metres from the near edge of the adjoining highway carriageway. Any sidewalls / fences / hedges adjacent to the access shall be splayed at an angle of 45 degrees from each of the (outside) gateposts to the front boundary of the site.
The reason for the condition is :-
In the interests of highway safety. |
| 3. | Prior to the commencement of the use hereby permitted, the proposed access / on-site parking / servicing / loading, unloading / turning / waiting area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter free from any impediment to that specific use.
The reason for the condition is :-
To ensure the permanent availability of the parking / manoeuvring area, in the interests of highway safety. |
| 4. | Prior to the occupation of the building, a flood response plan shall be submitted to and agreed in writing with the Local Planning Authority.
The reason for the condition is :-
To minimise the risk to the occupants in the event of flooding. |
| 5. | Prior to the commencement of development, details of construction methodology together with supporting calculations shall be submitted to and agreed in writing with the Local Planning Authority. The submitted calculations shall be sufficient to prove that the buildings will be constructed to withstand both hydrostatic and hydrodynamic pressures associated with a breach in the defence adjacent to the dwellings. All buildings are to be constructed in accordance with the agreed methodology.
The reason for the condition is :-
To maintain the structural integrity of the buildings in the event of a failure of the defences. |
| 6. | REASON FOR APPROVAL OF THE APPLICATION :- The temporary building is for required for employment related uses for a limited period of time and meets the criteria for employment related uses in the port area in accordance with the relevant policies in the Great Yarmouth Borough Wide Local Plan 2001. |
| 7. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with the NPPF. |